Strategic Environmental Assessment

Scoping Report

for the

Orkney Local Development Plan

October 2024

IMAGE: The Orkney Islands Council crest appears above the title “Strategic Environmental Assessment Scoping Report for the Orkney Local Development Plan”, dated “October 2024”.

Cover Note

PART 1

To: SEA_Gateway@gov.scot, SEA Gateway, 2 H (South), Victoria Quay, Edinburgh, EH6 6QQ

PART 2

An SEA Scoping Report is attached for the plan, programme or strategy (PPS) entitled:

Orkney Local Development Plan

The Responsible Authority is:

Orkney Islands Council

PART 3

☑ The PPS falls under the scope of Section 5(3) of the Act and requires an SEA under the Environmental Assessment (Scotland) Act 2005.

☐ The PPS falls under the scope of Section 5(4) of the Act and requires an SEA under the Environmental Assessment (Scotland) Act 2005.

☐ The PPS does not require an SEA under the Environmental Assessment (Scotland) Act 2005. However, we wish to carry out an SEA on a voluntary basis. We accept that, as this SEA is voluntary, the statutory 5 week timescale for views from the Consultation Authorities cannot be guaranteed.

PART 4

Contact name: Nina Caudrey

Job Title: Environmental Planner

Contact address: Development and Marine Planning, Neighbourhood Services and Infrastructure, Orkney Islands Council, School Place, Kirkwall, Orkney, KW15 1NY

Contact tel no: 01856 873535

Contact email: nina.caudrey@orkney.gov.uk

PART 5

Signature
(electronic signature is acceptable): Nina Caudrey

Date: 23 October 2024

Table of Contents

  1. Context
  2. Scoping information
  3. Proposed assessment methodology
  4. Next steps
  5. Annex I: Other plans, programmes and strategies
  6. Annex II: Baseline environmental data
  7. Annex II: Protected area condition data

Note: Baseline environmental information is provided in a separate document.

1. Context

a. Background

The plan being assessed is the future Orkney Local Development Plan (LDP). The Plan is a ten year plan covering the whole of the Orkney Islands Council area (figure 1) for the period 2027 – 2037.

Having a Local Development Plan is a legislative requirement under the Town and Country Planning (Scotland) Act 1997 (as amended). The purpose of the LDP is to set out a spatial strategy and the planning authority’s policies and proposals about how land is developed and used in the Orkney Islands Council area.

IMAGE: Map of the Orkney Islands showing the area covered by the Local Development Plan, including the main islands, settlements, transport routes, ferries, airports, lochs and hills.

Map of Orkney by Mikenorton [CC BY-SA 3.0], via Wikimedia Commons

Figure 1 – the area covered by the LDP

b. Environmental protection objectives in other plans, programmes and strategies

There are a large number of other plans, programmes and strategies (PPS) that are of relevance to the LDP. Due to their number, these are listed in Annex I: Other plans, programmes and strategies. The PPS are categorised according to their international, national and local scales and are accompanied by information on their purpose, relationship with the LPD and their relevance to the environmental assessment.

2. Scoping information

a. Topics considered

Schedule 3 of the Environmental Assessment (Scotland) Act 2005 lists categories of potential environmental effects that should be considered as part of the environmental assessment process. These have been grouped together into eight Topic areas. The Topics are:

  • Topic 1: Climatic Factors
  • Topic 2: Air
  • Topic 3: Water
  • Topic 4: Soil (including geodiversity)
  • Topic 5: Material Assets
  • Topic 6: Biodiversity
  • Topic 7: Landscape and Cultural Heritage
  • Topic 8: Population and Human Health

b. Topics scoped in

All the SEA Topics identified in section 2.a have been scoped in, as the LDP has the potential to influence all topics.

c. Environmental baseline

The separate Topic papers present information on the environmental baseline, ordered by the eight different topic areas: climatic factors, air, water, soils and geodiversity, material assets, biodiversity, landscape and cultural heritage, population and human health.

3. Proposed assessment methodology

a. Process

The intended SEA process is to:

  • Gather environmental baseline data and information, identify draft methodology.
  • Consult on the scoping report, to confirm the environmental baseline is complete and agree the assessment methodology with consultation authorities (current stage).
  • Alongside the preparation of LDP, carry out environmental assessment and prepare a draft Environmental Report for the LDP, using the assessment methodology and taking into account consultation authority advice on the scoping report.
  • Consult on the draft Environmental Report and LDP, followed by consideration of consultation feedback, before final sign off by the Council to submit to Ministers.
  • Issue a post-adoption statement on the Environmental Report.
  • Monitor environmental effects, identify and implement mitigation where unexpected adverse effects occur.

b. Assessment templates and SEA objectives

At this stage, it is intended that the assessment will focus on the elements that have the potential to result in changes, development or activities on the ground that may have environmental effects. Tables 1, 2 and 3 will be used as a basis for carrying out the environmental assessment and recording the findings. Table 1 provides the intended scoring matrix that will be used to ensure consistency during the environmental assessment. Tables 2 and 3 provide the main objectives and template for scoring and recording potential environmental effects during the environmental assessment. It incorporates proposed SEA objectives and sub-objectives that each element of the LDP will be scored against.

Where available, guidance published by the consultation authorities has been used as a basis for setting the SEA objectives and sub-objectives. These relate to the specific SEA environmental receptors and issues that have the potential to be affected by the LDP. The information and issues identified as part of the baseline have also been used to inform which objectives and sub-objectives are relevant to the environmental assessment of the LDP.

The SEA objectives and questions are provisional and may be modified during the SEA process – for example, as a result of comments from the Consultation Authorities, changes in the baseline data when it is fully collected and/or if the content of the LDP covers different subject matter than currently expected.

Table 1 – proposed scoring matrix

Significance of EffectScore
Element would have a major positive environmental effect in its current form as it would resolve an existing issue or maximise opportunities. SIGNIFICANT.++
Element would have a minor positive environmental effect.+
Effect of element is uncertain.?
No connectivity with the environmental Topic/Objective being assessed.x
Element would have no predicted environmental effects.0
Element would have a minor adverse environmental effect.-
The element would have a major adverse environmental effect as it would create significant new problems or substantially exacerbate existing problems. Consider exclusion of option. SIGNIFICANT.--

Table 2 – proposed main environmental objectives

TopicObjective numberMain Objective(s)
Climatic factors1aReduce the emissions of greenhouse gases with particular focus on emissions from buildings, transport, waste, energy generation and industry, and those arising from land use, land change and forestry (including natural carbon sinks such as peatlands, sea grass, kelp and trees).
Climatic factors1bEnsure existing and proposed infrastructure and buildings are located and designed to cope with future climate conditions.
Air2aTo maintain or improve air quality and reduce emissions of key pollutants.
Water3aMaintain and improve the quality of water resources and to protect and enhance the state of the water environment.
Water3bReduce demand for water and minimise unnecessary water use.
Water3cTo reduce the impact of invasive non-native species on the water environment.
Soil and geodiversity4aMinimise contamination and safeguard and improve soil, peat quality and geodiversity.
Material assets5aEncourage the sustainable use and reuse of material assets.
Biodiversity6aProtect and enhance the biodiversity of the Orkney.
Landscape and cultural heritage7aProtect and enhance the character, diversity and special qualities of the landscapes of Orkney.
Landscape and cultural heritage7bProtect and enhance the historic and cultural environment and assets (including linguistic) of Orkney.
Population and human health8aSupport and enhance the health and wellbeing of residents and visitors to Orkney through housing, recreation and employment opportunities.

Table 3 – proposed environmental assessment template

SEA objectiveSEA sub-objectiveNature of effectScoring: significance of effect before mitigationMitigation and enhancementScoring: residual significance of effect after mitigation
1aWill there be an effect on transport GHG emissions during construction activity or during operation/occupation?Insert a description of the nature of the potential effect the Option will have on the issue against the criteria set out by the SEA Objective. Include consideration of cumulative effects. Link to baseline information as necessary.Insert scoring for the significance of the environmental effect BEFORE mitigation (using the symbology in Table 1).Insert information on how adverse effects will be mitigated and/or how enhancements will be used to create positive effects.Insert scoring for the residual significance of the environmental effect AFTER mitigation (using the symbology in Table 1).
1aWill there be an effect on energy GHG emissions during construction activity or during operation/occupation?
1aWill there be an effect on industrial, manufacture and/or construction processes GHG emissions during construction activity or during operation/occupation?
1aWill there be an effect on waste GHG emissions during construction activity or during operation/occupation?
1aWill there be an effect on land use, land change and forestry GHG emissions during construction or during operation/occupation affecting carbon sinks (such as trees, carbon rich soils, wetlands, sea grass beds, kelp forests, etc)?
1bConsidering future implications of climate change (eg increased severity of weather resulting in more flooding, periods of drought and extremes of temperature), will there be an effect on existing infrastructure and buildings?
1bConsidering future implications of climate change (eg increased severity of weather resulting in more flooding, periods of drought and extremes of temperature), will there be an effect on infrastructure and buildings proposed in the Local Development Plan?
2aWill there be an effect on the levels of UK National Air Quality pollutants (e.g. NO₂, PM₁₀, PM₂.₅, SO₂)?
2aWill there be an effect on the levels of other types of air pollution (eg particulates)?
3aWill there be an effect on the water quality of watercourses and groundwater from diffuse and point source pollution?
3aWill there be an effect on the ability of catchments to store water and the natural flood management services they provide?
3aWill there be an effect on public water supplies?
3bWill there be an effect on demand for water from development (residential and business)?
3bWill there be an effect on sustainable use of water resources?
3cWill there be an effect on the water environment from invasive non-native species?
4aWill there be an effect on carbon rich soils?
4aWill there be an effect on soil sealing, soil structure and soil loss?
4aWill there be an effect on the levels of soil contamination?
4aWill there be an effect on soil erosion and landslides?
4aWill there be an effect on geodiversity interests (eg GCR sites)?
5aWill there be an effect on sustainable use of natural resources (eg water, aggregates)?
5aWill there be an effect on the sustainable use and management of existing and proposed infrastructure (eg water, heat, energy or flood protection infrastructure)?
5aWill there be an effect on the use of finite resources through the use of secondary and recycled materials?
6aWill there be an effect on the favourable condition of the interests of areas protected for nature conservation? (European sites, Ramsar sites, Sites of Special Scientific Interest)
6aWill there be an effect on protected species?
6aWill there be an effect on Scottish Biodiversity List habitats and plants found in Orkney? (in Local Nature Conservation Sites or in the wider countryside)
6aWill there be an effect on Scottish Biodiversity List non-plant species? (in Local Nature Conservation Sites or in the wider countryside)
6aWill there be an effect on invasive non-native species or tree pests and diseases?
7aWill there be an effect on the special qualities of the National Scenic Area?
7aWill there be an effect landscape character and local distinctiveness?
7bWill there be an effect on the historic and cultural environment and assets?
8aWill there be an effect on housing for local needs?
8aWill there be an effect on recreation and active travel opportunities that support healthier lifestyles?
8aWill there be an effect on employment opportunities local to places of residence?

c. Longevity and permanence of effects

Consideration of longevity and scale of effects is built into the assessment table template, so will form an integral part of the environmental assessment for each element assessed.

d. Alternatives and mitigation

At this stage, initial thinking is that consideration will be given to an LDP approach that focusses the majority of new development around existing settlements and to an alternative that spreads new development throughout settlements and the wider countryside. Other alternatives will be considered and assessed if different options emerge during the preparation of the consultation draft as well as from the public consultation itself.

e. Cumulative and in-combination effects

Consideration of the potential for cumulative and in-combination effects will be included as an integral part of the environmental assessment process for individual elements of the plan. A review of the assessment results will also be undertaken to double check any cumulative or in-combination effects that may not have been apparent during individual assessments.

f. Other environmental assessments

A Habitats Regulations Appraisal (HRA) will be undertaken to inform the LDP. While the HRA is required under different legislation, as a matter of good practice the HRA will be used to inform the Environmental Report and vice versa as part of an iterative process.

  1. Conservation (Natural Habitats, &c.) Regulations 1994, commonly referred to as the Habitats Regulations.

4. Next steps

a. Scoping advice sought from consultation authorities

As described in the previous sections, all Topics have been scoped in. OIC wish to seek the particular advice of the consultation authorities on:

  • the proposed methodology (section 3)
  • whether there are gaps in the environmental baseline information identified in separate Topic papers
  • if there is new information that is expected to become available over the next 3 months that could be useful to add to the environmental baseline.

The advice of the consultation authorities will be valuable for informing the environmental assessment going forward.

b. Environmental Report proposed consultation period

A round of public consultation events and a public call for sites was undertaken in Orkney during the summer of 2024, closing at the end of September. All proposed allocation sites will be subject to SEA (and HRA where required). At the current early stage of plan preparation, it is considered that the majority of the policies in National Planning Framework 4 (NPF4) will be appropriate for use in the Orkney context. As NPF4 policies have already been subject to SEA (and HRA), such policies will be scoped out of the SEA of the Orkney LDP. However any new policies and any NPF4 policies that require local adaptation for the Orkney LDP will be subject to SEA (and HRA where required). A twelve week consultation period is therefore anticipated for the Environmental Report.

c. Indicative timescales for plan preparation and consultation

It is anticipated that the LDP and the Environmental Report will be consulted on at the same time via the SEA Gateway. They will also go out for public consultation during this time.

Annex I: Other plans, programmes and strategies

Relevant PPSRelevant objectives/purposeSEA topicRelationship between the PPS and land use planning
International directives and policies
European Landscape Convention (European Commission, 2000)Promotes the protection, management and planning of European landscapes and organises European co-operation on landscape issues.biodiversity; landscape and cultural heritage; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should be a tool for the maintenance and restoration of landscapes and their natural habitats.
The Paris Agreement (United Nations Framework Convention on Climate Change, 2015)The agreement sets out a global action plan to put the world on track to avoid dangerous climate change by limiting global warming to well below 2°C and pursuing efforts to limit it to 1.5°C.climatic factorsWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should seek to promote the development and use of appropriate renewable energy sources and contribute to climate change mitigation.
Kyoto Protocol (UNFCCC, 1997)Protocol to the international Framework Convention on Climate Change Framework with the objective of reducing the Greenhouse gases that cause climate change.climatic factorsWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support measures that will reduce greenhouse gas emissions.
The Pan-European Biological and Landscape Diversity Strategy (Council of Europe, 1995)The Strategy aims to reverse the decline of landscape and biological diversity, by promoting innovation and proactive policy making.biodiversity; landscape and cultural heritage; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support the strategy by considering the contribution that actions could make to protecting biodiversity and landscapes.
Ramsar Convention on Wetlands of International Importance 1971Requires conservation and wise use of wetlands.water; biodiversity; landscape and cultural heritageWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should ensure the protection and enhancement of wetlands.
Taking Sustainable Use of Resources Forward: A thematic Strategy on the prevention and recycling of waste (EU 2005)A sector based strategy produced as a requirement of the Seventh Environmental Action Programme of the European Community, seeking to help Europe become a recycling society that seeks to avoid waste and uses waste as a resource.climatic factors; air; material assetsWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should seek to minimise waste and promote recycling.
Thematic Strategy for Soil Protection (EU 2006)A sector based strategy produced as a requirement of the Seventh Environmental Action Programme of the European Community, seeking to establish common principles for the protection and sustainable use of soils.soil and geodiversityWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should contribute towards the protection and improvement of soil.
UN Convention on Biological Diversity (UN, 1992)An international legally-binding treaty with three main goals: conservation of biodiversity; sustainable use of biodiversity; fair and equitable sharing of the benefits arising from the use of genetic resources.biodiversityWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should look for opportunities to conserve, and where possible restore, biodiversity.
UN Framework Convention on Climate Change (the Rio Earth Summit) 1992 (UN, 1992)Treaty aimed at reducing global emissions of greenhouse gases to combat global warming.climatic factorsWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should assist in the reduction of greenhouse gas emissions.
National legislation (UK and Scotland)
Air Quality (Scotland) Regulations 2000 (as amended in Scotland)Establishes standards for air quality and sets limits for various pollutants in Scotland.air; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support measures that would improve air quality.
Ancient Monuments and Archaeological Areas Act 1979 (as amended by Historic Environment (Amendment) (Scotland) Act 2011)Prescribes the approach to be taken to planning for scheduled ancient monuments and archaeological areas.landscape and cultural heritageWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should ensure that scheduled ancient monuments and archaeological areas are not adversely affected by new development.
Climate Change (Scotland) Act 2009Legislation to set a target for the year 2050, an interim target for the year 2020, and to provide for annual targets, for the reduction of greenhouse gas emissions; to provide about the giving of advice to the Scottish Ministers relating to climate change; to confer power on Ministers to impose climate change duties on public bodies; to make further provision about mitigation of and adaptation to climate change; to make provision about energy efficiency, including provision enabling council tax discounts; to make provision about the reduction and recycling of waste; and for connected purposes.climatic factorsWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support and include climate change adaptation and mitigation measures.
Conservation (Natural Habitats, &c) Regulations 1994 (as amended for Scotland)These regulations relate to the designation of European sites, and provision of protection to various plant and animal species.biodiversityWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should ensure that European sites are protected from loss or damage.
Environment Act 1995The Act sets new standards for environmental management by statutory bodies.all topicsThe council must adhere to the standards set out in the act.
Environmental Assessment (Scotland) Act 2005Requires Strategic Environmental Assessments to be completed for plans, programmes and strategies likely to have significant environmental effects.all topicsEnables the significant environmental effects of the plan, programme or strategy being assessed to be identified and addressed.
Environmental Impact Assessment (Forestry) (Scotland) Regulations 2017Requires environmental impact assessments for certain forestry projects.all topicsThe plan, programme or strategy being assessed will be required to be compatible with environmental impact assessments legislation.
The Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2017Requires environmental impact assessment of site specific projects and specifically requires consideration of Sensitive Areas.all topicsThe plan, programme or strategy being assessed will be required to be compatible with environmental impact assessments legislation.
Equality Act 2010The Equality Act 2010 legally protects people from discrimination in the workplace and in wider society.population and human healthThe plan, programme or strategy being assessed should ensure that it does not result in individuals or groups with protected characteristics being discriminated against.
Flood Risk Management (Scotland) Act 2009Establishes roles, responsibilities and requirements for sustainable flood management.climatic factors; water; population and human healthThe plan, programme or strategy being assessed should support flood management, particularly natural flood management.
Historic Environment Scotland Act 2014Amongst other things, establishes Historic Environment Scotland with the general function of investigating, caring for and promoting Scotland's historic environment.landscape and cultural heritageThe plan, programme or strategy being assessed should support the protection and preservation of the historic environment.
Housing (Scotland) Act 2014Makes provision about housing, including provision about the abolition of the right to buy, social housing, the law affecting private housing, the regulation of letting agents and the licensing of sites for mobile homes.population and human healthThe plan, programme or strategy being assessed should support the provision of housing, particularly affordable housing.
Islands (Scotland) Act 2018Sets out a requirement for public bodies to have regard to the effects on island communities in relation to their policies and plans.population and human healthThe plan, programme or strategy being assessed can identify development opportunities that enable islands communities.
National Plan for Scotland’s Islands (December 2019)The National Islands Plan provides a framework for action in order to meaningfully improve outcomes for island communities.population and human healthThe plan, programme or strategy being assessed can identify development opportunities that enable islands communities.
Land Reform (Scotland) Act 2003Establishes right of responsible access to land and water.water; landscape and cultural heritage; biodiversity; population and human healthThe plan, programme or strategy being assessed can provide for and support responsible access.
Nature Conservation Act (Scotland) 2004Act places duties on public bodies for conserving biodiversity, increases protection for Sites of Special Scientific Interest (SSSI), amends legislation on Nature Conservation Orders, provides for Land Management Orders for SSSIs and associated land, strengthens wildlife enforcement legislation, and requires the preparation of a Scottish Fossil Code.water; biodiversity; landscape and cultural heritageWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support conservation and enhancement of biodiversity.
National Planning Framework 4 (NPF4)Sets out national development plan and policies as a framework to inform LDPs.all topicsThe plan, programme or strategy subject to SEA must ensure that it complies with NPF4.
Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997Prescribes the approach to be taken in planning for listed buildings, conservation areas and designed landscapes and gardens.material assets; landscape and cultural heritageWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should ensure that listed buildings, conservation areas and designed landscapes and gardens are not adversely affected.
Sewage (Scotland) Act 1968Along with the Water Industry (Scotland) Act 2002 this gives responsibilities to Scottish Water to manage the discharge of surface water that enters its drainage systems (by providing sewers and public Sustainable Urban Drainage Systems (SUDs)) and to maintain water supplies and drainage infrastructure.water; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should have regard to Scottish Water’s duties under this act.
Water Environment and Water Services (Scotland) Act 2003Transposes the Water Framework Directive into Scots law.water; biodiversity; landscape and cultural heritage; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should encourage improvements to the water environment and support measures for more efficient use of water.
Water Industry (Scotland) Act 2002Along with the Sewage (Scotland) Act 1968 this gives responsibilities to Scottish Water to manage the discharge of surface water that enters its drainage systems (by providing sewers and public Sustainable Urban Drainage Systems (SUDs)) and to maintain water supplies and drainage infrastructure.water; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should have regard to Scottish Water’s duties under this act.
Wildlife and Countryside Act 1981 (as amended in Scotland)Sets out offences in relation to the protection of certain species.biodiversityWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support protected species.
Wildlife and Natural Environment (Scotland) Act 2011Amends Wildlife and Countryside Act 1981, and seeks to modernise game law; abolish the designation ‘areas of special protection’; improve snaring practice; regulate invasive non-native species; change the licensing system for protected species; amend current arrangements for deer management and deer stalking; strengthen protection of badgers; change how muirburn can be practised; and make operational changes to the management of Sites of Scientific Interest; game law, use of shores, and invasive species legislation.biodiversityWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support provisions of the act.
Nature Conservation (Scotland) Act 2004To make provision in relation to the conservation of biodiversity; to make further provision in relation to the conservation and enhancement of Scotland’s natural features; to amend the law relating to the protection of certain birds, animals and plants; and for connected purposes.biodiversityWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support provisions of the act.
National policy (UK and Scotland)
The Air Quality (Scotland) Regulations 2000Sets out air quality objectives for Scotland.air; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should encourage reductions in emissions through a range of measures.
Creating Places - A policy statement on architecture and place for Scotland (Scottish Government, 2013)A policy statement on architecture and place setting out the comprehensive value good design can deliver. The document contains an action plan that sets out the work that will be taken forward to achieve positive change.landscape and cultural heritage; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support good design.
Climate ready Scotland - Scottish Climate Change Adaptation Programme 2019 – 2024 (Scottish Government, 2019)Sets objectives in relation to adaptation to climate change, Ministerial proposals and policies for meeting those objectives, and the period within which those proposals and policies will be introduced. The Programme also sets out the arrangements for wider engagement in meeting those objectives.climatic factors; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should encourage reductions in emissions through a range of measures.
Civil Contingencies Act 2004Delivers a framework for civil protection in the UK and defines the responsibilities for responders to emergency which include (among others).material assets; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support the requirements of responders to fulfil their statutory duties.
Cleaner Air for Scotland 2 – The Road to a Healthier Future (Scottish Government, 2021)The national cross-government strategy that sets out how the Scottish Government and its partner organisations propose to reduce air pollution further to protect human health and fulfil Scotland’s legal responsibilities as soon as possible.air; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should encourage reductions in emissions through a range of measures.
Groundwater Protection Policy for Scotland (SEPA, 2009)This policy aims to provide a sustainable future for Scotland’s groundwater resources by protecting legitimate uses of groundwater and providing a common SEPA framework.water; soil and geodiversityWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should aim, where possible, to manage significant flood risk to groundwater from flooding related pollution.
Historic Environment Circular 1 (HES, 2019)This circular covers the requirements of the secondary legislation (‘the Regulations’) relating to the Historic Environment Scotland Act 2014 (‘the 2014 Act’).landscape and cultural heritageWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should follow the guidance for policy development on the management of the historic environment.
Historic Environment Policy Statement (HES, 2019)Document to which planning authorities are directed in their consideration of applications for conservation area consent, listed building consent for buildings of all three categories and their consideration of planning applications affecting the historic environment and the setting of individual elements of the historic environment.landscape and cultural heritageWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should follow the guidance for policy development on the management of the historic environment.
Land Use Strategy for Scotland 2021 – 2026 (Scottish Government, 2021)Outlines strategy for achieving sustainable land use across Scotland and getting the best from the land of Scotland.all topicsWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA could provide more specific direction on the national land use strategy and can be implemented at a regional level.
Managing Change in the Historic Environment Guidance Notes (HES, various)Series of guidance notes which are designed to support the Scottish Historic Environment Policy (SHEP) and Scottish Planning Policy.landscape and cultural heritageWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support positive management of the historic environment.
Control of Woodland Removal Policy (Scottish Government, 2009)Sets out Scottish Ministers policy on woodland removal in Scotland.climatic factors; water; soil and geodiversity; biodiversity; landscape and cultural heritageWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support the policy.
The River Basin Management Plan for the Scotland River Basin District: 2015–2027 (SEPA, 2015)Fulfils a requirement under the Water Environment and Water Services (Scotland) Act 2003.water; soil and geodiversity; biodiversityWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support management objectives for water bodies.
Scotland’s National Transport Strategy (Transport Scotland, 2020)Scottish Government’s National Strategy for reducing transport emissions by 80%.climatic factors; air; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support reductions in emissions from transport.
Scottish Biodiversity Strategy (Scottish Government, 2022 in draft)Identifies Scottish biodiversity priorities.water; biodiversity; landscape and cultural heritageWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should reflect the purpose of the strategy.
Scottish Government’s Infrastructure Investment Plan (Scottish Government, 2021)Gives an overview of the Scottish Government's plans for infrastructure investment over the coming decades.material assets; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should take account of potential impacts (both positive and negative) of actions on existing and planned developments.
Scottish Government’s National Performance Framework, National Outcomes (Scottish Government, undated)As part of the National Performance Framework, Scottish Government have set 15 National Outcomes that the public sector must collectively deliver, on children and young people, economy, fair work and business, international, communities, education, health, poverty, culture, environment, human rights.all topicsWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should identify and contribute to delivery of the outcomes that are most appropriate in the plan/programme/strategy area.
Scottish Soil Framework (Scottish Government, 2009)Ministers policies and objectives for the conservation and use of soils.all topicsWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should promote soil conservation.
Scottish Water Business Plan 2015 – 2021 (Scottish Water, 2015)The business plan sets out how Scottish Water will deliver improvements to drinking water quality, the environment and customer service required by Scottish Ministers.water; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should be developed with regard to the objectives and actions proposed in the business plan.
Scottish Zero Waste Plan (Scottish Government, 2010)Provides context for waste planning in Scotland by sets the strategic direction for waste policy for Scotland, with a target of 70% recycling and maximum 5% to landfill by 2025 for all Scotland's waste.climatic factors; soil and geodiversity; material assets; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA support waste management and good design.
Local plans and strategies
Orkney Islands Council Core Paths Plan (OIC, 2018)Identifies a network of core paths throughout the Orkney Council area.biodiversity; population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support the promotion and development of core paths.
Orkney Community Plan (incorporating the Local Outcome Improvement Plan) (prepared by Community Planning Partners)Strategic documents outlining (usually socio-economic) priorities for communities. Community Planning Partners include local public services such as councils, NHS boards, police and fire services, and other public bodies. They work together to improve the way that local services are planned, co-ordinated and carried out.all topicsWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should help deliver priorities to address inequalities and issues in communities.
Local Housing StrategyRequired by the Housing (Scotland) Act 2001. Sets out how housing authorities will provide for housing needs and demands in their area.population and human healthWhere relevant to the priorities identified, the proposals in the plan, programme or strategy subject to SEA should support housing delivery.
Local Transport StrategySet out how to maintain and improve infrastructure.climatic factors; air; population and human healthPlan should support sustainable transport solutions and encourage lower carbon forms of transport.

Annex II: Baseline environmental data

Please see the separate Topic paper infographic document.

Annex II: Protected area condition data

Data correct at time of download from https://informatics.sepa.org.uk/ProtectedNatureSites/ using Orkney Islands Council area as a locational filter on 23 August 2024.

Site NameDesignationFeature NameSummary ConditionPressurePressure Recorded As
HoySACVegetated sea cliffsFavourableOver grazingGrazing - over
HoySACAlpine and subalpine heathsFavourableOver grazingGrazing - over
HoySACAlpine and subalpine heathsFavourableRecreation/disturbanceRecreation/disturbance
HoySACBase-rich fensFavourableAgricultural operationsAgricultural operations
HoySACPlants in crevices on base-rich rocksFavourableNatural eventNatural event
Loch of IsbisterSACNaturally nutrient-rich lakes or lochs which are often dominated by pondweedRecoveringTramplingTrampling
Loch of IsbisterSACNaturally nutrient-rich lakes or lochs which are often dominated by pondweedRecoveringWater managementWater Dependant Pressure- diffuse source pollution
Loch of IsbisterSACOtter (Lutra lutra)FavourableTramplingTrampling
Loch of IsbisterSACOtter (Lutra lutra)FavourableWater managementWater Dependant Pressure- diffuse source pollution
Loch of IsbisterSACVery wet mires often identified by an unstable 'quaking' surfaceFavourableGrazing - otherGrazing - appropriate level
Loch of StennessSACLagoonsFavourableAgricultural operationsAgricultural operations
Loch of StennessSACLagoonsFavourableWater managementWater management
Stromness Heaths and CoastSACBase-rich fensFavourableGrazing - otherGrazing - appropriate level
AuskerrySPAArctic tern (Sterna paradisaea), breedingUnfavourableOtherNo on-site activities related to feature condition noted
Calf of EdaySPACormorant (Phalacrocorax carbo), breedingFavourableAgricultural operationsAgricultural operations
Calf of EdaySPAGreat black-backed gull (Larus marinus), breedingUnfavourableAgricultural operationsAgricultural operations
Calf of EdaySPASeabird assemblage, breedingUnfavourableOtherNo on-site activities related to feature condition noted
CopinsaySPAGuillemot (Uria aalge), breedingUnfavourableClimate ChangeClimate change
CopinsaySPAKittiwake (Rissa tridactyla), breedingUnfavourableClimate ChangeClimate change
CopinsaySPASeabird assemblage, breedingUnfavourableClimate ChangeClimate change
Orkney Mainland MoorsSPARed-throated diver (Gavia stellata), breedingFavourableInvasive speciesPresence/changing extent invasive species - NATIVE
SwithaSPAGreenland barnacle goose (Branta leucopsis), non-breedingFavourableAgricultural operationsAgricultural operations
Calf of EdaySSSICormorant (Phalacrocorax carbo), breedingFavourableAgricultural operationsAgricultural operations
Central SandaySSSIMachairUnfavourableInvasive speciesPresence/changing extent invasive species - NATIVE
Central SandaySSSIMachairUnfavourableOver grazingGrazing - over
Central SandaySSSISand dunesUnfavourableInvasive speciesPresence/changing extent invasive species - NATIVE
Central SandaySSSISand dunesUnfavourableOver grazingGrazing - over
CopinsaySSSIGuillemot (Uria aalge), breedingUnfavourableClimate ChangeClimate change
CopinsaySSSIKittiwake (Rissa tridactyla), breedingUnfavourableClimate ChangeClimate change
CopinsaySSSISeabird colony, breedingUnfavourableClimate ChangeClimate change
Cruaday QuarrySSSISilurian - Devonian ChordataFavourableExtractionMineral extraction
Den WickSSSIQuaternary of ScotlandFavourableDumping/storage of materialsDumping/spreading/storage of materials
Den WickSSSIQuaternary of ScotlandFavourableNatural eventNatural event
Doomy and Whitemaw HillSSSIArctic skua (Stercorarius parasiticus), breedingUnfavourableClimate ChangeClimate change
Doomy and Whitemaw HillSSSIWhimbrel (Numenius phaeopus), breedingUnfavourableClimate ChangeClimate change
Doomy and Whitemaw HillSSSIWhimbrel (Numenius phaeopus), breedingUnfavourableDumping/storage of materialsDumping/spreading/storage of materials
Doomy and Whitemaw HillSSSIWhimbrel (Numenius phaeopus), breedingUnfavourableOtherOther activity
Doomy and Whitemaw HillSSSIWhimbrel (Numenius phaeopus), breedingUnfavourableOver grazingGrazing - over
Glims Moss and Durka DaleSSSIHydromorphological mire rangeFavourableInvasive speciesPresence/changing extent invasive species - NATIVE
Glims Moss and Durka DaleSSSIHydromorphological mire rangeFavourableNatural eventNatural event
Glims Moss and Durka DaleSSSIRaised bogFavourableNo proactive managementLack of remedial management
Holm of Papa WestraySSSIBlack guillemot (Cepphus grylle), breedingUnfavourableOtherOther activity
HoySSSICoastal Geomorphology of ScotlandFavourableOtherNo on-site activities related to feature condition noted
HoySSSIUpland oak woodlandFavourablePlant pests and diseasesPlant Pests and Diseases
Keelylang Hill and Swartaback BurnSSSIBreeding bird assemblageFavourableBurningBurning
Loch of BanksSSSIBreeding bird assemblageFavourableTo be identifiedPressure to be identified
Loch of BanksSSSIBreeding bird assemblageFavourableWater managementWater management
Loch of BanksSSSIHen harrier (Circus cyaneus), non-breedingRecoveringOtherOther activity
Loch of BanksSSSIBasin fenUnfavourableInvasive speciesPresence/changing extent invasive species - NATIVE
Loch of BanksSSSIBasin fenUnfavourableUnder grazingGrazing - under
Loch of Isbister and the LoonsSSSIBreeding bird assemblageFavourableWater managementWater management
Loch of Isbister and the LoonsSSSIBasin fenFavourableGrazing - otherGrazing - appropriate level
Lochs of Harray and StennessSSSITufted duck (Aythya fuligula), non-breedingUnfavourableTo be identifiedPressure to be identified
Lochs of Harray and StennessSSSIEutrophic lochUnfavourableInvasive speciesPresence/changing extent invasive species - NON NATIVE
Lochs of Harray and StennessSSSIEutrophic lochUnfavourableWater managementWater Dependant Pressure- diffuse source pollution
Lochs of Harray and StennessSSSIFreshwater nerite snail (Theodoxus fluviatilis)FavourableWater managementWater Dependant Pressure- diffuse source pollution
Lochs of Harray and StennessSSSISaline lagoonFavourableAgricultural operationsAgricultural operations
Lochs of Harray and StennessSSSISaline lagoonFavourableWater managementWater management
Mill LochSSSIRed-throated diver (Gavia stellata), breedingFavourableGame/fisheries managementFishing - recreational
Mill LochSSSIRed-throated diver (Gavia stellata), breedingFavourableInter-specific competitionInter-specific competition
RousaySSSIBreeding bird assemblageFavourableInvasive speciesPresence or changing extent of invasive species
RousaySSSIBreeding bird assemblageFavourableWater managementWater management
RousaySSSIMesotrophic lochUnfavourableInvasive speciesPresence or changing extent of invasive species
RousaySSSIMesotrophic lochUnfavourableWater managementWater management
RousaySSSIBlanket bogFavourableOtherOther activity
RousaySSSIVascular plant assemblageFavourableWater managementWater Dependant Pressure- flow regulation
Stromness Heaths and CoastSSSINon-marine DevonianFavourableDumping/storage of materialsDumping/spreading/storage of materials
Stromness Heaths and CoastSSSINon-marine DevonianFavourableExtractionGeological Core extraction
Stromness Heaths and CoastSSSINon-marine DevonianFavourableRecreation/disturbanceFossil Collection
SwithaSSSIGreenland barnacle goose (Branta leucopsis), non-breedingFavourableAgricultural operationsAgricultural operations
West Mainland MoorlandsSSSIRed-throated diver (Gavia stellata), breedingFavourableInvasive speciesPresence/changing extent invasive species - NATIVE
West Mainland MoorlandsSSSIBlanket bogFavourableExtractionMineral extraction
West Mainland MoorlandsSSSIBlanket bogFavourableInvasive speciesPresence/changing extent invasive species - NATIVE
West Mainland MoorlandsSSSIBlanket bogFavourableOtherOther activity
West Mainland MoorlandsSSSIUpland assemblageFavourableInvasive speciesPresence/changing extent invasive species - NATIVE
West Mainland MoorlandsSSSIUpland assemblageFavourableWater managementWater management
West WestraySSSIMaritime cliffFavourableGrazing - otherGrazing - appropriate level