Item: 7

Enterprise and Infrastructure Committee: 10 November 2026

Road Asset Replacement Programme – Expenditure Monitoring

Report by Head of Finance.

1. Overview

1.1

This report presents the summary position of expenditure incurred as at 30 September 2026, in respect of the approved Road Asset Replacement Programme for 2026/27.

1.2

To demonstrate a focus on maintaining existing assets of the Council and ensuring that our buildings and infrastructure are maintained at levels expected by the Orkney public and that our IT, plant and vehicles achieve modern standards of security, safety and emissions, annual capital improvement and replacement programmes of work are agreed by the relevant service Committee or Sub-committee.

1.3

Delivery of these planned programmes of work are thereafter monitored throughout the financial year by the relevant service Committee or Sub-committee.

1.4

The Roads Asset Replacement Programme budget was temporarily increased to £1.5 million for financial years 2025/26, 2026/27 and 2027/28, as a result of a recommendation by the Policy and Resources Committee on 18 June 2024, to demonstrate a focus on maintaining existing assets.

1.5

The annual Road Asset Replacement Programme for financial year 2026/27 was approved by the Enterprise and Infrastructure Committee on 3 February 2026.

1.6

To support the delivery of additional works, the programme has been allocated £654,000 in additional funding, consisting of £534,000 from the Islands Accelerator Fund and £120,000 from Scottish Government Connectivity funding for 2026/27.

1.7

The table below provides an overview of the expenditure incurred for the period 1 April to 30 September 2026.

Project DescriptionExpenditure as at 30 September 2026Annual Budget 2026/27Probable Out-turn 2026/27Overspend/(Underspend)
Road Asset Replacement Programme£541,897£2,154,000£1,838,206(£315,794)

1.8

To mitigate the underspend, the Roads team is actively identifying additional works that can be incorporated into the 2026/27 programme.

1.9

Appendix 1 to this report provides a detailed breakdown of the approved programmes of work for financial year 2026/27, including individual project updates.

2. Recommendations

2.1

It is recommended that members of the Committee:

  1. Note the summary position of expenditure incurred as at 30 September 2026, against the approved Road Asset Replacement Programme for financial year 2026/27, as detailed in section 1.7 of this report.

  2. Note the detailed analysis of expenditure figures and programme updates, in respect of the approved Road Asset Replacement Programme for 2026/27 attached as Appendix 1 to this report.

For Further Information please contact:

Shonagh Merriman, Service Manager (Corporate Finance), extension 2105, Email shonagh.merriman@orkney.gov.uk

Implications of Report

  1. Financial The Financial Regulations state that Directors can incur expenditure within approved revenue and capital budgets. Such expenditure must be in accordance with the Council’s policies and objectives and subject to compliance with the Financial Regulations.

  2. Legal Regular financial monitoring and reporting helps the Council meet its statutory obligation to secure best value.

  3. Corporate Governance In terms of the Scheme of Administration, monitoring, on a quarterly basis, the levels of expenditure incurred against the approved road asset improvement programme, funded through the approved capital programme, is referred to the Enterprise and Infrastructure Committee.

  4. Human Resources N/A

  5. Equalities Equality Impact Assessment is not required for financial monitoring.

  6. Island Communities Impact Island Communities Impact Assessment is not required for financial monitoring.

  7. Links to Council Plan The proposals in this report support and contribute to improved outcomes for communities as outlined in the following Council Plan strategic priorities:

    • ☐ Growing our economy.
    • ☐ Strengthening our Communities.
    • ☐ Developing our Infrastructure.
    • ☐ Transforming our Council.
  8. Links to Local Outcomes Improvement Plan The proposals in this report support and contribute to improved outcomes for communities as outlined in the following Local Outcomes Improvement Plan priorities:

    • ☐ Cost of Living.
    • ☐ Sustainable Development.
    • ☐ Local Equality.
    • ☐ Improving Population Health.
  9. Environmental and Climate Risk Where resources allow, improvement works can include ‘greener’ solutions.

  10. Risk Improvement of existing assets can help reduce risks associated with these assets.

  11. Procurement Any contractual arrangements require to comply with the Financial Regulations and Contract Standing Orders.

  12. Health and Safety Well-maintained assets will assist the Council in complying with relevant Health and Safety requirements for both staff and the public.

  13. Property and Assets Included throughout the report and detailed in the Appendix.

  14. Information Technology N/A.

  15. Cost of Living N/A.

List of Background Papers

Enterprise and Infrastructure Committee, 3 February 2026, Road Asset Replacement Programmes for 2026/27.

Appendix

Appendix 1 – Road Asset Replacement Programme 2026/27 Q2.

Appendix 1

Roads Asset Replacement Programme 2026/2027

Project descriptionActual spend to 30/09/2026 (£)Budget (£)Probable out-turn (£)Overspend/(Underspend) (£)
B9061 Mount Pleasant and Bay of Bomastay, Stronsay

Protection against coastal erosion.

Development Management have requested a screening application for this work which will have a knock on effect to the completion timescale of this project.

The works will be postponed for this year and moved to a future asset replacement programme.
0100,0000(100,000)
Houton - Rock Armour

Protection against coastal erosion.

Works with Engineering Services to design and tender. Expected completion by the end of financial year 2026/27.
18330,00030,0000
Germiston Road - Brig repair

Structural repair of the Brig.

Ecological surveys delayed the final design of this project and meant the best weather window was missed for this year. Works proposed to be postponed until summer 2027 when water levels are minimal and the works can be carried out quicker and safer.
0100,0000(100,000)
Bridges and Structures183230,00030,000(200,000)
Slater Street, Kirkwall - Lay new kerbs and surface

Defective kerbing and footway surface to be upgraded.

On works programme. To be completed over the winter 2026/27.
020,00020,0000
A961 Burray - Lay new kerbs and footway reconstruction

Associated with A961 Burray haunch works. Works Cancelled for 26.27. Budget Reallocated

Works postponed to financial year 2027/28 to allow for bore hole testing to be carried out and a Tensar grid foundation design to be prepared due to significant depth of sand underground at this location.
020,0000(20,000)
Bellevue Park - Lay new kerbs and surface

Associated with streetlighting cabling works.

Works are planned to be completed over winter 2026/27. Full budget expected to be spent.
030,00030,0000
Solar Panel Replacement for weather stations

Solar Panel Replacement for weather stations

Order confirmed with the supplier and will be invoiced and paid when the equipment has been supplied and installed later this financial year.
025,00025,0000
Welfare Portacabins

Purchase of four welfare portacabins for Eday, Stronsay, Sanday and Shapinsay

Ongoing procurement for the purchase of these facilities. On track to be purchased and installed before the end of the financial year.
0120,000120,0000
Associated Infrastructure0215,000195,000(20,000)
A965 near Atlantis Lodges, Finstown

Upgrade existing drainage and outfall.
£15,000 - carry over from Atlantis Lodges work started in 2025/26.
£37,000 - repair outfall, new pipes & headwall.

Remainder of works extended into this financial year are now complete. Carried over works as part of an ongoing contract which included drainage, resurfacing and carriageway reconstruction at this location.

The budget figure represents the best estimate split of each remaining phase of work at the time of preparing the asset replacement programme, based upon the remaining value of the contract. Final site measurements and valuations on completion of the work provided a more accurate figure to attribute the remaining contract costs to.
40,00052,00040,000(12,000)
Lindisfarne, Westray - Upgrade existing drainage and outfall

Culvert works, pipework upgrade and tideflex installation.

Works currently being designed and will be instructed to our operations team for completion before the end of financial year 2026/27.
025,00025,0000
Bay of Greentoft, Eday - Upgrade existing drainage and outfall

Repair outfall. New pipes and headwalls.

Awaiting site visit and final design. Expected to be fully spent by end of the financial year.
060,00060,0000
Stromness Pumping Station - Drainage

Stromness Pumping Station - Drainage

Works complete. Effective working time on site was limited due to tidal conditions which increased labour costs for the project which led to the overspend.
61,76940,00061,76921,769
Drainage101,769177,000186,7699,769
Germiston Road, Orphir - Overlay Surfacing

Improvement of carriageway surface. Budget Reallocated.

Expenditure from works carried out at the end of last financial year that was not invoiced in time to be paid from last year's budget.
23,854023,85423,854
A961 Highland Park - Inlay Surfacing

Improvement of carriageway surface.

Works complete. Overspend relates to additional labour and plant hire costs from works taking slightly longer than planned.
30,53925,00030,5395,539
A965 near Atlantis Lodges, Finstown - Inlay Surfacing

Carry over from Atlantis Lodges work started in 2025/26.

Remainder of works extended into this financial year are now complete. Carried over works as part of an ongoing contract which included drainage, resurfacing and carriageway reconstruction at this location.

The budget figure represents the best estimate split of each remaining phase of work at the time of preparing the asset replacement programme, based upon the remaining value of the contract. Final site measurements and valuations on completion of the work provided a more accurate figure to attribute the remaining contract costs to.
38,00030,00038,0008,000
Castle Street, Kirkwall - Inlay Surfacing

Improvement of carriageway surface.

Works complete. Additional works included to replace some carriageway ironwork contributed to slight overspend.
83,20680,00083,2063,206
B9056 North of Yesnaby Junction - Inlay Surfacing

Improvement of carriageway surface. Budget reallocated

This project was removed from the capital asset replacement programme and will be surface dressed in summer 2027 instead.
0000
Back Road / Church Road, St Margaret's Hope - Inlay Surfacing

Improvement of carriageway surface. Back Road / Church Road, St Margarets Hope.

Works currently ongoing. Expected to be completed by mid November.
0125,000125,0000
Investigation works 2027 - Surfacing Projects

Test holes.

No investigation works carried out yet. Geological survey work planned for A961 near Leaburn in Burray for future reconstruction works planned for 2027/28. Survey works will be carried out this financial year.
010,00010,0000
Pickaquoy Road, Kirkwall - Inlay Surfacing

Tesco zebra crossing to Crafty car park access. Plus section from junction with Muddisdale Road to joint of existing patch near Picky Loan.

Works programmed for October school holidays. The project outturn reflects the agreed programme of works and efficiencies realised during delivery.
0190,00098,627(91,373)
Noup Road, Westray - Inlay Surfacing

Inlay Surfacing, Noup Road.

Works programmed for October school holidays.

The project outturn reflects the agreed programme of works and efficiencies realised during delivery.
070,00062,798(7,202)
Crowness Crescent, Kirkwall - Inlay Surfacing

Inlay Surfacing, Crowness Crescent.

Works programmed and will be completed by the end of the financial year.
065,00065,0000
A965 Finstown West - Inlay Surfacing

Worst section between Grandon Road and 30mph speed limit.

Contract awarded and works in progress. Expected to be completed by end of 2026.
0160,000160,0000
Laing Street, Kirkwall - Inlay Surfacing

Full extent, Laing Street, Kirkwall.

On planned works programme. Due to be completed at the end of November 2026.
045,00045,0000
Muddiesdale Road, Kirkwall - Inlay Surfacing

From Picky Road to just past junction to Muddisdale car park plus approx 5m into the junction for the road leading to Muddisdale car park. Plus remaining 3 speed bumps along Muddisdale Road (include approx 5m each side of the speed bumps). Plus overlay on Care Home access part at the end of Muddisdale Road.

Works complete. Small extra cost incurred after final site measurement resulted in actual works being slightly more than initially estimated.
3,81770,00073,8523,852
Mill Street, Kirkwall - Inlay Surfacing

From junction with King Street to just past OIC car park access.

On planned works programme. Due to be completed by the end of 2026.
040,00040,0000
Howe Road, Stromness - Inlay Surfacing

Inlay Surfacing, Howe Road.

Works were completed mid October. Awaiting final costings to be charged to the project.
020,00020,0000
Surface Treatments179,415930,000875,875(54,125)
B9056 North of Yesnaby Junction - Carriageway reconstruction

Carriageway strengthening and improvement associated with surfacing works. Budget of £15k reallocated

This project was removed from the capital asset replacement programme and will be surface dressed in summer 2027 instead.
0000
Germiston Road, Orphir - Carriageway reconstruction

Carriageway strengthening and improvement associated with surfacing works. Budget Reallocated.

Expenditure from works carried out at the end of last financial year that was not invoiced in time to be paid from last year's budget.
1,00001,0001,000
Church Road, St Margaret's Hope - Carriageway reconstruction

Carriageway strengthening and improvement associated with surfacing works.

Works currently ongoing. Expected to be completed by mid November.
020,00020,0000
A961 Burray Village - Carriageway reconstruction

Carriageway strengthening and improvement on failed section.

Works postponed to financial year 2027/28 to allow for bore hole testing to be carried out and a Tensar grid foundation design to be prepared due to significant depth of sand underground at this location.
0125,0000(125,000)
Old Scapa Road, Kirkwall - Carriageway reconstruction

Carriageway edge strengthening and improvement.

Works recently completed. Still awaiting all final costs to be invoiced and allocated to the job. Final expenditure will end up closer to the budgeted figure.
81,277130,000130,0000
A965 Finstown - Haunch reconstruction

Carry over from Atlantis Lodges work started in 2025/26.

Remainder of works extended into this financial year are now complete. Carried over works as part of an ongoing contract which included drainage, resurfacing and carriageway reconstruction at this location.

The budget figure represents the best estimate split of each remaining phase of work at the time of preparing the asset replacement programme, based upon the remaining value of the contract. Final site measurements and valuations on completion of the work provided a more accurate figure to attribute the remaining contract costs to.
46,66620,00046,66626,666
A966 Rendall - Haunch reconstruction

Carriageway edge strengthening & improvement.

Carry over cost from works that were carried out at the end of 2025/26 and could not be fully completed in time before the new financial year. Overspend relates to unforeseen additional works that were required during the project, including replacement of broken culvert slabs on several culverts and additional dig depth for sections where soft ground conditions were encountered.
75,40253,00075,40222,402
B9055 Brodgar - Haunch reconstruction

Carriageway edge strengthening & improvement. Budget Reallocated

Moved to a future programme.
0000
A965 Finstown West - Haunch reconstruction

Carriageway edge strengthening & improvement, A965 Finstown West.

Contract awarded and works in progress. Expected to be completed by end of 2026.
771155,000155,0000
A965 Rennibister - Haunch reconstruction

Carry over from Rennibister works started in 2025/26.

Works completed last financial year.
0000
A960 St Andrews Reconstruction

A960 St Andrews Reconstruction - carry over costs from 25.26

Expenditure from works carried out at the end of last financial year that was not invoiced in time to be paid from last year's budget.
16,994016,99416,994
Roads Reconstruction222,110503,000445,062(57,938)
Helliar View, Shapinsay - Replace Columns

2 columns (CA04 & 05) to be replaced in same location. Replace columns over 30yrs old. HV01 - HV05.

Works recently completed and awaiting final invoices to be allocated to the job. Full budget expected to be spent.
015,00015,0000
Kirkwall, Stromness, Westray & Longhope - Replace columns only

Replace 18 obsolete Corus folding columns: B9047 Longhope LH05N - LH07N; Pier Road, Longhope PR01 - PR03; Coplands Lane, Kirkwall CO01 & CO02; Market Green, Stromness MG06 - MG08; Gill Pier GP01; Stromness School Path SA14 - SA16; Lane between Kirklands Road and Scapa Crescent SC15 & SC20.

Works ongoing. Current expenditure reflects works completed so far. Final expenditure expected to match the budget.
7,47050,00050,0000
Bellevue Park, Kirkwall - Replace columns, cabling and control systems

Replace columns over 30yrs old and upgrade control/cabling.

Works are planned to be completed over winter 2026/27. Full budget expected to be spent.
33224,00024,0000
Liberator Drive, Kirkwall - LED lantern upgrade

Replacement of old Thorn Lanterns with new signify lanterns. 31 in total.

Current expenditure includes an overcharge which has been investigated and will be amended. The final cost is expected to be £16,500. Overspend relates to additional electrician labour cost and unplanned cabling works within some columns due to condition of existing wiring being significantly worse than expected as a result of water ingress through some of the old lanterns.
30,61710,00016,5006,500
Street Lighting38,41999,000105,5006,500
Roads Asset Replacement Programme 2026/2027541,8972,154,0001,838,206(315,794)