1.1

This report presents the revenue financial summary position of expenditure incurred, as at 30 September 2026, in respect of service areas for which the Enterprise and Infrastructure Committee is responsible.

1.2

On 10 March 2026, the Council set its overall revenue budget for financial year 2026/27. On 16 June 2026, the Policy and Resources Committee recommended approval of the detailed revenue budgets for 2026/27, which form the basis of the individual revenue expenditure monitoring reports.

1.3

Individual revenue expenditure monitoring reports are circulated every month to inform elected members of the up-to-date financial position. Quarterly revenue expenditure monitoring reports are presented to individual service committees.

1.4

In terms of revenue spending, at an individual cost centre level, budget holders are required to provide an explanation of the causes of each material variance and to identify appropriate corrective actions to remedy the situation.

1.5

Material variances are identified automatically as Priority Actions within individual budget cost centres according to the following criteria:

  • Variance of £10,000 and more than 110% or less than 90% of anticipated position (1B).
  • Not more than 110% or less than 90% of anticipated position but variance greater than £50,000 (1C).

1.6

Priority Actions can be identified at the Service Function level according to the same criteria and these are shown in the Revenue Expenditure Statements. As with individual cost centre variances, each of these Priority Actions requires an explanation and corrective action to be identified and these are shown in the Budget Action Plan.

1.7

The details have been provided following consultation with the relevant Directors and their staff.

1.8

The figures quoted within the Budget Action Plan by way of the underspend (-) and overspend position will always relate to the position within the current month.

2. Recommendations

2.1

It is recommended that members of the Committee:

  1. Note the revenue financial summary statement in respect of service areas for which the Enterprise and Infrastructure Committee is responsible, for the period 1 April to 30 September 2026, attached as Annex 1 to this report, indicating a budget overspend position of £109,100.
  2. Note the revenue financial service area statement in respect of service areas for which the Enterprise and Infrastructure Committee is responsible, for the period 1 April to 30 September 2026, attached as Annex 2 to this report.
  3. Note the explanations given and actions proposed in respect of significant budget variances, as outlined in the Budget Action Plan, attached as Annex 3 to this report.

For Further Information please contact:

Pat Robinson, Service Manager (Accounting), extension 2621, Email: pat.robinson@orkney.gov.uk

Implications of Report

  1. Financial — The Financial Regulations state that Directors can incur expenditure within approved revenue and capital budgets. Such expenditure must be in accordance with the Council’s policies and objectives and subject to compliance with the Financial Regulations.
  2. Legal — Regular financial monitoring and reporting help the Council meet its statutory obligation to secure best value.
  3. Corporate Governance — In terms of the Scheme of Administration, monitoring the levels of revenue expenditure incurred against approved budgets, in respect of each of the service areas for which the Committee is responsible, is referred to the Enterprise and Infrastructure Committee.
  4. Human Resources — N/A.
  5. Equalities — Equality Impact Assessment is not required for financial monitoring.
  6. Island Communities Impact — Island Communities Impact Assessment is not required for financial monitoring.
  7. Links to Council Plan: The proposals in this report support and contribute to improved outcomes for communities as outlined in the following Council Plan strategic priorities:
    • ☐ Growing our economy.
    • ☐ Strengthening our Communities.
    • ☐ Developing our Infrastructure.
    • ☐ Transforming our Council.
  8. Links to Local Outcomes Improvement Plan: The proposals in this report support and contribute to improved outcomes for communities as outlined in the following Local Outcomes Improvement Plan priorities:
    • ☐ Cost of Living.
    • ☐ Sustainable Development.
    • ☐ Local Equality.
    • ☐ Improving Population Health.
  9. Environmental and Climate Risk — N/A.
  10. Risk — N/A.
  11. Procurement — N/A.
  12. Health and Safety — N/A.
  13. Property and Assets — N/A.
  14. Information Technology — N/A.
  15. Cost of Living — N/A.

List of Background Papers

  • Policy and Resources Committee, 3 March 2026, Budget and Council Tax Level for 2026/27.
  • Policy and Resources Committee, 16 June 2026, Detailed Revenue Budgets.

Annexes

  • Annex 1: Financial Summary.
  • Annex 2: Financial Detail by Service Area.
  • Annex 3: Budget Action Plan.

Annex 1: Financial Summary

September 2026

The table below provides a summary of the position across all Service Areas.

General Fund

Service AreaSpend £000Budget £000Over/(Under) Spend £000Spend %Annual Budget £000
Roads2,483.72,633.5(149.8)94.34,431.4
Transportation13,407.713,199.4208.3101.633,547.4
Operational Environmental Services1,435.91,149.0286.9125.03,486.4
Environmental Health & Trading Standards488.2510.8(22.6)95.61,310.6
Development1,344.41,286.757.7104.52,829.2
Planning391.3662.7(271.4)59.01,690.5
Service Totals19,551.219,442.1109.1100.647,295.5

Compared to last month, the total number of PAs has changed as follows:

Service AreaNo. of PAs P05No. of PAs P06Service FunctionsPAs/Function
Roads541233%
Transportation77888%
Operational Environmental Services45683%
Environmental Health & Trading Standards0030%
Development521118%
Planning35683%
Totals24234650%

Date of Issue - 16 October 2026

Annex 2: Financial Detail by Service Area

September 2026

The following tables show the spending position by service function.

General Fund

Roads

FunctionPASpend £000Budget £000Over/(Under) Spend £000Spend %Annual Budget £000
Winter Maintenance and Response375.2346.328.9108.31,278.6
Street Lighting70.675.1(4.5)94.0260.3
Car Parks1B10.3(52.6)62.9N/A(39.3)
Other Works43.445.2(1.8)96.0135.0
Traffic Management278.1291.5(13.4)95.4373.5
Structural Maintenance991.61,011.9(20.3)98.01,671.6
Routine Maintenance611.1623.6(12.5)98.01,028.0
Quarries Holding Account1B210.8(74.5)285.3N/A(500.0)
Roads Holding Account1B(10.8)366.5(377.3)N/A0.0
Fleet Holding Account1B(102.3)(14.9)(87.4)686.60.0
Movement in Reserves0.00.00.00.091.6
Miscellaneous - RD5.715.4(9.7)37.0132.1
Service Total2,483.72,633.5(149.8)94.34,431.4

Transportation

FunctionPASpend £000Budget £000Over/(Under) Spend £000Spend %Annual Budget £000
Administration - TR1B78.7100.5(21.8)78.3297.0
Co-ordination1B62.318.943.4329.664.2
Concessionary Fares1B185.8135.450.4137.2320.5
Support for Operators - Buses1B488.1587.6(99.5)83.11,500.1
Support for Operators - Air747.3738.68.7101.21,772.8
Support for Operators - Ferries1B244.41.4243.017,457.13.4
Airfields Operations1B427.0348.478.6122.6712.4
Orkney Ferries1C11,174.111,268.6(94.5)99.228,877.0
Service Total13,407.713,199.4208.3101.633,547.4

Changes in original budget position:

Annual Budget £000
Original Net Budget33,569.8
Kirkwall Travel Centre(22.4)
Total33,547.4

Date of Issue - 16 October 2026

Operational Environmental Services

FunctionPASpend £000Budget £000Over/(Under) Spend £000Spend %Annual Budget £000
Burial Grounds60.154.85.3109.7104.4
Refuse Collection1B(328.3)(290.1)(38.2)113.2699.7
Waste Disposal1B1,151.0713.6437.4161.31,489.5
Recycling1B366.9325.941.0112.6675.3
Environmental Cleansing1B167.1222.8(55.7)75.0517.5
OES Holding Account1B19.1122.0(102.9)15.70.0
Service Total1,435.91,149.0286.9125.03,486.4

Environmental Health & Trading Standards

FunctionPASpend £000Budget £000Over/(Under) Spend £000Spend %Annual Budget £000
Administration - ES283.2308.3(25.1)91.9839.3
Trading Standards133.1136.1(3.0)97.8341.8
Public Toilets71.966.45.5108.3129.5
Service Total488.2510.8(22.6)95.61,310.6

Development

FunctionPASpend £000Budget £000Over/(Under) Spend £000Spend %Annual Budget £000
Heritage Development132.3146.7(14.4)90.2191.7
Museums251.2258.2(7.0)97.3503.2
St Magnus Cathedral195.2202.5(7.3)96.4357.9
Administration - DV385.8372.113.7103.71,013.8
Business Gateway84.982.82.1102.5183.1
UK Shared Prosperity Fund1B22.3(7.2)29.5N/A116.7
Community Led Local Development (CLLD)344.7335.79.0102.7730.6
Regeneration(460.6)(462.4)1.899.60.0
Economic Development Grants1B14.81.213.61,233.3282.6
Other Economic Development Grants373.8357.116.7104.7516.3
Movement in Reserves0.00.00.00.0(1,066.7)
Service Total1,344.41,286.757.7104.52,829.2

Date of Issue - 16 October 2026

Planning

FunctionPASpend £000Budget £000Over/(Under) Spend £000Spend %Annual Budget £000
Administration - PL1B68.079.6(11.6)85.4457.8
Development Management1B102.0191.3(89.3)53.3381.3
Development Planning1B251.7315.4(63.7)79.8671.0
Building Standards1B(90.4)47.7(138.1)N/A116.2
Archaeology29.030.0(1.0)96.764.2
North Isles Landscape Partnership Scheme1B31.0(1.3)32.3N/A0.0
Service Total391.3662.7(271.4)59.01,690.5

Changes in original budget position:

Annual Budget £000
Original Net Budget1,690.3
NILPS – Budget Realignment0.2
Total1,690.5

Date of Issue - 16 October 2026

Annex 3: Budget Action Plan

September 2026

Roads

FunctionFunction Description/ExplanationAction Category/Action DescriptionResponsible OfficerDeadlineStatus
R26DCar Parks

Less than anticipated income by £62.9K

Budget position is dependent on income which varies across the year. However, the position as at 30 September has been impacted by the cost of repairs and electricity for the EV chargers.
No action required

Income from the car parks has never met budget expectations, resulting in this cost centre being overspent year on year despite a change in the income target being applied in 2025/26. Increasing car park charges will reduce usage, and hence income, and so the service attempts to set tariffs that represent a balance between income generation and encouraging usage.
Lorna Richardson31/12/2026Ongoing
R26LQuarries Holding Account

Less than anticipated income by £285.3K

Ageing plant in need of significant maintenance means that additional, unbudgeted, costs have been incurred.
Monitor the situation

Plans are being progressed for an overhaul of plant and machinery using additional capital grant funding provided to the Council. The team continue to work to ensure that products match the local market demand with a view to increasing income.
Lorna Richardson31/12/2026Ongoing
R26MRoads Holding Account

Less than anticipated expenditure by £377.3K

Quarry purchases are now being charged directly to the relevant cost centres rather than being processed through this function area.
Management input required

A review of how costs are transferred will take place to determine what budget reprofiling may be required.
Lorna Richardson31/12/2026Ongoing

Date of Issue - 21 October 2026

Roads

FunctionFunction Description/ExplanationAction Category/Action DescriptionResponsible OfficerDeadlineStatus
R26NFleet Holding Account

More than anticipated income by £87.4K

Income is ahead of expectations as the garage team has increased in size and more work can be done (and invoiced) than in the past.
Monitor the situation

No action at this time, noting that income is dependent on work carried out and work continues to replace the aging fleet and improve resilience.
Lorna Richardson31/12/2026Ongoing

Date of Issue - 21 October 2026

Transportation

FunctionFunction Description/ExplanationAction Category/Action DescriptionResponsible OfficerDeadlineStatus
R27AAdministration - TR

Less than anticipated expenditure by £21.8K

Underspend within staff costs due to vacancy.
No action required

No action required as expected to appoint to the vacancy in October.
Gareth Waterson30/10/2026Ongoing
R27BCo-ordination

More than anticipated expenditure by £43.4K

Property costs are ahead of the budget profile, and this is mainly due to an increase in rates paid on the Bus Station, and associated facilities.
Raise virements request

Virement will be processed to realign the budget with actual expenditure.
Gareth Waterson30/10/2026Ongoing
R27CConcessionary Fares

More than anticipated expenditure by £50.4K

Due to an ageing population, and the introduction of the under 22 travel scheme, the uptake of the local concessionary travel scheme is increasing and therefore it is likely that the actual spend will be higher than the full year budget.
Monitor the situation

Will continue to monitor. Concessionary fares to be considered under wider fare review/islander discount proposals.
Gareth Waterson31/12/2026Ongoing

Date of Issue - 21 October 2026

Transportation

FunctionFunction Description/ExplanationAction Category/Action DescriptionResponsible OfficerDeadlineStatus
R27GSupport for Operators - Buses

Less than anticipated expenditure by £99.5K

Income from bus fares continues to be higher than anticipated as bus passenger figures continue to rise. Bus passenger income is credited to the Sustainable and Green Transport Fund.
No action required

The extra income in the Sustainable and Green Transport Fund is welcome, and this fund is used to run transport initiatives and support other budgets where required, such as the runway maintenance programme.
Gareth Waterson31/12/2026Ongoing
R27JSupport for Operators - Ferries

More than anticipated expenditure by £243.0K

Budget not yet created for the expenditure in this code relating to the Ferry Replacement Programme.
Raise virements request

Process virement to create budget.
Gareth Waterson31/12/2026Ongoing

Date of Issue - 21 October 2026

Transportation

FunctionFunction Description/ExplanationAction Category/Action DescriptionResponsible OfficerDeadlineStatus
R27KAirfields Operations

More than anticipated expenditure by £78.6K

Increase in staff costs relating to several new recruits at different airfields, therefore there has been an increased need for additional hours for training and compliance. In addition, aerodrome licence fees to the Civil Aviation Authority of £29.5K and insurance costs of £21.8K have been incurred in the first half of the financial year.
Management input required

Manage future expenditure to bring actuals more in line with the annual budget and process a virement from other areas within the Service to transfer budget to cover any overspends where necessary. Undertake virement, if necessary, to reprofile spend on annual payments.
Gareth Waterson31/12/2026Ongoing
R27LOrkney Ferries

Less than anticipated expenditure by £94.5K

The underspend position is primarily attributable to the following factors: refund received from SSEN, Ferry Replacement Programme recharge income, and seasonal positions being recruited through Orkney Ferries rather than OIC for operational reasons.
No action required

No action required.
Gareth Waterson30/10/2026Ongoing

Date of Issue - 21 October 2026

Operational Environmental Services

FunctionFunction Description/ExplanationAction Category/Action DescriptionResponsible OfficerDeadlineStatus
R28CRefuse Collection

More than anticipated income by £38.2K

Income ahead of prediction due to increased uptake in commercial waste services.
Monitor the situation

There may be a need to re-baseline income expectations, as a result of the increase in commercial customers. This will be monitored and reviewed by the service, noting that income from commercial waste services is designed to cover the actual cost of providing the service.
Lorna Richardson31/12/2026Ongoing
R28EWaste Disposal

More than anticipated expenditure by £437.4K

Costs of waste disposal are higher than available budget, due to increases in plant and labour costs. Income from recyclates is variable and difficult to profile.
Monitor the situation

The Council has no control over the amount of waste generated and which then needs to be processed, transported and disposed of. Increased costs relating to all aspects of this mean that this function area is under immense pressure. The service continues to look for opportunities for increasing recycling rates, as income from these can help to offset transportation costs, and for other efficiencies in service delivery.
Lorna Richardson31/03/2027Ongoing
R28FRecycling

More than anticipated expenditure by £41.0K

Repair costs for essential vehicle and plant have been higher than anticipated.
Monitor the situation

Work is ongoing to improve the fleet and create greater resilience however this will inevitably take several years. In the interim strengthened processes around management and maintenance of vehicles are in place.
Lorna Richardson31/12/2026New

Date of Issue - 21 October 2026

Operational Environmental Services

FunctionFunction Description/ExplanationAction Category/Action DescriptionResponsible OfficerDeadlineStatus
R28GEnvironmental Cleansing

Less than anticipated expenditure by £55.7K

Less work than anticipated has been carried out due to resource pressures and operatives being needed elsewhere.
Monitor the situation

Operatives continue to be used where priority dictates, noting that any underspend in this area will be required to contribute in overspend in others.
Lorna Richardson31/12/2026Ongoing
R28KOES Holding Account

Less than anticipated expenditure by £102.9K

Cost recovery is ahead of profile.
Monitor the situation

Actual cost recovery should align with the income profile over the coming months, however, a review of charge rates will also be carried out, to ensure that they are set at the appropriate level.
Lorna Richardson31/12/2026Ongoing

Date of Issue - 21 October 2026

Development

FunctionFunction Description/ExplanationAction Category/Action DescriptionResponsible OfficerDeadlineStatus
R33CUK Shared Prosperity Fund

Less than anticipated income by £29.5K

Crown Estate monies require to be transferred into the UKSPF cost centre to meet staff costs as agreed by Council.
Raise journals request

Raise journal to set up transfer between cost centres.
Sweyn Johnston30/10/2026Ongoing
R33JEconomic Development Grants

More than anticipated expenditure by £13.6K

Grant claims paid to date is ahead of the anticipated budget.
Raise virements request

Process virement to realign the budget with actual spend incurred.
Sweyn Johnston30/10/2026Ongoing

Date of Issue - 21 October 2026

Planning

FunctionFunction Description/ExplanationAction Category/Action DescriptionResponsible OfficerDeadlineStatus
R34AAdministration - PL

Less than anticipated expenditure by £11.6K

The underspend here relates to a staff vacancy, which is now pending a decision in recruitment as part of the Corporate Admin review.
No action required

No action required in the meantime.
Gavin Barr31/12/2026Ongoing
R34BDevelopment Management

Less than anticipated expenditure by £89.3K

Substantial application fee received during the quarter. We are also due to incur expenditure over the next 2-3 months which should return spend closer to the anticipated profile.
Monitor the situation

Variance should correct itself as spend is required on consultants etc. in the coming months. We are also currently engaging with Finance to review historic profiles to see if it is possible to forecast profiling more accurately.
Gavin Barr31/12/2026Ongoing
R34CDevelopment Planning

More than anticipated income by £63.7K

Income received from Scottish Government in relation to Marine Planning is ahead of the anticipated budget profile.
Raise virement request

Virement will be processed to realign budget with actual income and expenditure.
Gavin Barr30/10/2026New

Date of Issue - 21 October 2026

Planning

FunctionFunction Description/ExplanationAction Category/Action DescriptionResponsible OfficerDeadlineStatus
R34EBuilding Standards

Less than anticipated expenditure by £138.1K

Fee income continues to be healthy and ahead of profile. It is expected that the budget profile will pick up as financial year continues.
Monitor the situation

Engagement with Finance is currently taking place regarding setting more realistic budget profiling.
Gavin Barr31/12/2026Ongoing
R34MNorth Isles Landscape Partnership Scheme

More than anticipated expenditure by £32.3K

Grant claims paid to date is ahead of the anticipated budget profile.
Raise virements request

Process virement to realign the budget with actual spend incurred to date.
Sweyn Johnston30/10/2026New