Skip to main content

The content below has been generated by an AI model. If anything is unclear, check the source document (opens in new tab) .

Item: 14

Education, Communities and Housing Committee: 11 November 2026

Housing Revenue Account

Revenue Repairs and Maintenance Programmes – Expenditure Monitoring

Report by Head of Finance

IMAGE: The first page bears the Orkney Islands Council crest and logo.

1. Overview

1.1

This report presents the summary position of expenditure incurred as at 30 September 2026 in respect of the approved Housing Revenue Account revenue repairs and maintenance programme for 2026/27.

1.2

To demonstrate a focus on monitoring the Repairs and Maintenance Programme which includes pre-planned work around the Scottish Housing Quality Standard, Energy Efficiency Standard for Social Housing, heating upgrades, servicing and other upgrades and replacements, reactive repairs that cover properties handed back by tenants, as well as repairs that are reported throughout the year which are agreed by the relevant service Committee or Sub-committee.

1.3

Delivery of these planned programmes of work are thereafter monitored throughout the financial year by the relevant service Committee or Sub-committee.

1.4

The annual programme of revenue repairs and maintenance for the Housing Revenue Account for financial year 2026/27 was approved by the Education, Communities and Housing Committee on 1 April 2026.

1.5

The table below provides an overview of the expenditure incurred as at 30 September 2026:

DescriptionActual Expenditure at 30 September 2026 (£000)Approved Budget 2026/27 (£000)Probable Out-turn 2026/27 (£000)Overspend/(Underspend) (£000)
Repairs and Maintenance Programme958.52,055.12,095.640.5
Total958.52,055.12,095.640.5

1.6

A detailed breakdown of the approved programme of work for financial year 2026/27, including individual project updates is attached at Appendix 1.

2. Recommendations

2.1

It is recommended that members of the Committee:

  1. Note the summary position of expenditure incurred, as at 30 September 2026, against the approved Housing Revenue Account revenue repairs and maintenance programme for 2026/27, as detailed in section 1.5 of this report.

  2. Note the detailed analysis of expenditure figures and approved programme updates in respect of the approved Housing Revenue Account revenue repairs and maintenance programme for 2026/27, attached as Appendix 1 to this report.

For Further Information please contact:

Pat Robinson, Service Manager (Accounting), extension 2621, Email: pat.robinson@orkney.gov.uk

Implications of Report

  1. Financial The Financial Regulations state that Directors can incur expenditure within approved revenue and capital budgets. Such expenditure must be in accordance with the Council’s policies and objectives and subject to compliance with the Financial Regulations.

  2. Legal Regular financial monitoring and reporting helps the Council meet its statutory obligation to secure best value.

  3. Corporate Governance In terms of the Scheme of Administration, monitoring the levels of expenditure incurred against the approved annual programme for improving and maintaining the existing Council housing stock, held on the Housing Revenue Account, funded through the approved capital programme and revenue budgets, is referred to the Education, Communities and Housing Committee.

  4. Human Resources N/A.

  5. Equalities An Equality Impact Assessment is not required for financial monitoring.

  6. Island Communities Impact An Island Communities Impact Assessment is not required for financial monitoring.

  7. Links to Council Plan The proposals in this report support and contribute to improved outcomes for communities as outlined in the following Council Plan strategic priorities:

  • ☐ Growing our economy.
  • ☐ Strengthening our communities.
  • ☐ Developing our Infrastructure.
  • ☐ Transforming our Council.
  1. Links to Local Outcomes Improvement Plan The proposals in this report support and contribute to improved outcomes for communities as outlined in the following Local Outcomes Improvement Plan priorities:
  • ☐ Cost of Living.
  • ☐ Sustainable Development.
  • ☐ Local Equality.
  • ☐ Improving Population Health.
  1. Environmental and Climate Risk Where resources allow, improvement works can include ‘greener’ solutions.

  2. Risk Improvement of existing assets can help reduce risks associated with these assets.

  3. Procurement Any contractual arrangements require to comply with the Financial Regulations and Contract Standing Orders.

  4. Health and Safety Well-maintained assets will assist the Council in complying with relevant Health and Safety requirements for both staff and the public.

  5. Property and Assets Included throughout the report and detailed in the Appendix.

  6. Information Technology N/A.

  7. Cost of Living N/A.

List of Background Papers

Education, Communities and Housing Committee, 1 April 2026, Housing Revenue Account Revenue Repairs and Maintenance Programme – Proposed Programme for 2026/27.

Appendix

Appendix 1 – Housing Revenue Account Revenue Repairs and Maintenance Monitoring Report as at 30 September 2026

Appendix 1

Repairs and Maintenance ProgrammeActual Expenditure 30 September 2026 (£000's)Approved Budget 2026/27 (£000's)Balance Remaining (£000's)Estimated Outturn 2026/27 P12 (£000's)Predicted Overspend / (Underspend) (£000's)Update
Cyclical Maintenance62.198.9(36.8)120.021.1A number of the planned preventive maintenance (PPM) works are expected to continue into Q3, with expenditure anticipated to increase during this quarter that may not be reflected until Q4.
Planned Maintenance206.7697.4(490.7)700.02.6Kitchen and Bathroom replacement contract progressing. Windows replacement contract underway with invoicing expected in Q3/Q4.
Reactive Repairs320.9444.7(123.8)450.05.3Reactive repairs broadly on target, but may move over Q3 and Q4 due to winter conditions.
Voids/Improvements/Adaptations368.8538.5(169.7)550.011.5Voids works progressing. A large number of void works emerged in Q2. A priority process has been agreed with Housing to restrict expenditure, this is monitored on a weekly basis.
In-House Professional Fees0.0275.6(275.6)275.60.0To be charged at year-end.
TOTALS958.52,055.1(1,096.6)2,095.640.5