Skip to main content

The content below has been generated by an AI model. If anything is unclear, check the source document (opens in new tab) .

Orkney Islands Council Local Development Plan

Delivery Programme March 2025

www.orkney.gov.uk

IMAGE: Cover photograph showing an Orkney landscape at sunset, with standing stones, sheep grazing in a field, the Orkney Islands Council crest, and the text “Orkney Islands Council Local Development Plan Delivery Programme March 2025” and “www.orkney.gov.uk”.

Contents

  • Introduction
  • Background
  • What is a Delivery Programme?
  • The Orkney Island Council Delivery Programme
  • Schedule 1 - Delivery Programme: Proposals
  • Schedule 2 - Delivery Programme: Policies

Introduction

The Council’s statutory local development plan when adopted in 2017 was accompanied by a Delivery Programme to support the delivery of the Local Development Plan. This Delivery Programme will replace the Delivery Programme adopted in 2017.

Background

In response to the letter received from the Chief Planner there has been a review undertaken of information contained in the existing Housing Land Audit, Strategic Housing Investment Plan and previous information from stakeholders and landowners to prepare an updated Delivery Plan for the existing Orkney Local Development Plan. This includes considering the information needed to show a Deliverable Housing Land Pipeline.

What is a Delivery Programme?

The purpose of the Delivery Programme is to support the delivery of the Orkney Island Council Local Development Plan 2017 (OLDP) by setting out the actions and partnerships that are necessary to implement the strategy of the Plan. In accordance with legislative requirements, the Delivery Programme, as a minimum, must set out:

  • a list of actions required to deliver policies and proposals contained in the OLDP;
  • an explanation as to how those actions are to be undertaken;
  • the timescale for the conclusion of each action; and
  • the expected sequencing of, and timescales for, delivery of housing on sites allocated by the LDP (a ‘housing delivery pipeline’).

The Orkney Island Council Delivery Programme

The Delivery Programme, set out at in Schedule 1 and 2, outlines the actions required to support future development across Orkney. The Delivery Programme is structured according to the different allocations in settlements and highlights where there is relevant infrastructure considerations needed to progress delivery. It also sets out actions needed to help deliver the policies contained in the Local Development Plan. With work underway on developing a new Local Development Plan many of the actions will form part of the review of the new Local Development Plan and sites will also be reviewed as part of the preparation of the new Local Development Plan.

It should be noted that many of the sites which are allocated for development within the Local Development Plan are within private ownership therefore the timing at which sites come forward is largely outwith the control of Planning Authority. However, the Delivery Programme can be a way to facilitate development.

On viewing the remaining allocated sites within the Local Development Plan there are still many allocated sites that are available for development. These are of various sizes and locations across the different settlements of Orkney.

The Housing Land Audit has consistently demonstrated that significant numbers of new houses are delivered in Orkney through windfall development. Windfall development means planning permission has been granted on sites not specifically allocated for development in the Local Development Plan so would apply to conversions of existing buildings, small-scale infill developments within settlements or as housing developments in the countryside. With the ad hoc nature of windfall development, it isn’t specifically covered in the Delivery Programme.

This Delivery Programme sets out a Delivery Pipeline with the expected timescales for delivery of housing on sites allocated by the OLDP categorised into short term: years 1-3, medium term: years 4-6 and long term: years 7-10.

The Delivery Programme will be a useful tool to help stimulate development within the allocated sites, highlighting where there is still capacity for development in the current Local Development Plan allocations. It will also assist in developing suitable approaches to development where closer work is needed with infrastructure providers and landowners and provide a resource to show where updates or further research is required to support policies for the next Local Development Plan.

Schedule 1 - Delivery Programme: Proposals

Kirkwall Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
KirkwallK-1HousingPrivateDevelopment Brief requiredLong TermNo progress--
KirkwallK-2HousingPrivateDevelopment Brief requiredLong TermNo progress--
KirkwallK-3HousingMixedDevelopment Brief required, SWMP outcomes neededLong TermPartially developedPart of site built out, application on private area of land submittedOIC owned land - no progress, Private Land - submission for housing received.
KirkwallK-5HousingMixed-Short TermPartially developedPhases on site with final stages approved-
KirkwallK-6HousingPublicUpdated Development Brief requiredMedium TermPartially developedCare Home on site, Housing Application approvedApplication approved for Care Home (21/069/PP) and Housing (19/014/PPMAJ). Care Home development on site.
KirkwallK-7HousingPrivateDevelopment Brief requiredMedium TermNo progress--
KirkwallK-8HousingPrivateNew Development Brief required, Scottish Water upgrades, Archaeology investigationsLong TermNo progress-Area within Highland Park Catchment
KirkwallK-9HousingPrivateScottish Water upgrades and DrainageMedium TermApplication Stage-Area within Highland Park Catchment
KirkwallK-10HousingPrivateReview of HSE offset, Infrastructure issuesLong TermSite on the market-Area within Highland Park Catchment
KirkwallK-11HousingPrivate-Long TermNo Progress-Area within Highland Park Catchment
KirkwallK-12HousingPrivate--No Progress--
KirkwallK-13HousingPrivate--No Progress--
KirkwallK-14HousingPublicDevelopment Brief required, SWMP outcomes neededLong TermNo Progress--
KirkwallK-15HousingPublicDevelopment Brief required, Infrastructure queries and accessLong TermNo progress-The existing Waterfield Development Brief does not cover all the allocation and will therefore have to be reviewed.
KirkwallK-16HousingPublicDeveloped-Completed--
KirkwallK-18Business & IndustrialPublic--No progress--
KirkwallK-19Business & IndustrialPublic--No progress--
KirkwallK-20Business & IndustrialPrivate-Medium TermNo progress--
KirkwallK-21Business & IndustrialPrivateJoint Development Brief with K-1 & K-2. Review of land use as part of next LDPLong TermNo progress-Submitted within call for sites as potential Housing land.
KirkwallK-22RedevelopmentPublicDevelopment Brief is required, Land contamination/mitigation surveys required, Heritage/building surveys requiredLong TermNo Progress-Site is still within ownership of NHS
KirkwallK-23Mixed UsePublicMixed use element of proposals requires funding. SEPA situation regarding coastal flooding requires resolution for housing development.Medium TermEarly concept-HOUSING - There is a coastal, fluvial and pluvial high flooding risk. Coastal flood risk issues with SEPA need to be resolved. Project exploring development opportunity for collections archive within part of the site.
KirkwallK-23Mixed UsePublicMixed use element of proposals requires funding. SEPA situation regarding coastal flooding requires resolution for housing development.Medium TermEarly concept-HOUSING - There is a coastal, fluvial and pluvial high risk flood risk on this site. Coastal flood risk issues with SEPA need to be resolved. Museums and stores exploring development opportunity for archive facility within part of the site, with later removal of former bowling alley building.
KirkwallK-24Mixed UsePrivateFlood Risk Management RequiredLong TermNo progress-HOUSING - There is a coastal, fluvial and pluvial high risk flood risk on this site. Coastal flood risk issues with SEPA need to be resolved.
KirkwallK-25Mixed UsePrivateJoint Development Brief/Masterplan required with K-26 & K-27. Phase 1 Archaeological study undertaken. Stage 1 Mitigation Survey undertakenLong TermTemporary Application for Retail/Leisure useTemporary application is being developed out on site.Permission given for temporary use for retail, leisure, open space and night club use. Application to make permanent would be required. SEPA coastal flooding issues across whole of site for sensitive uses.
KirkwallK-26Mixed UsePrivateJoint Development Brief/Masterplan required with K-26 & K-27. Phase 1 Archaeological study undertaken. Stage 1 Mitigation Survey undertakenLong TermNo progress-Recently sold. SEPA coastal flooding issues across whole of site for sensitive uses.
KirkwallK-27Mixed UsePrivateJoint Development Brief/Masterplan required with K-26 & K-27. Phase 1 Archaeological study undertaken. Stage 1 Mitigation Survey undertakenLong TermNo progress-Site still occupied by current users
KirkwallK-28Redevelopment SitePublicUpdated masterplan/development brief needed. Understanding of Education Service need for space/services. Program and plan for special school funding and land requirementsLong TermEarly discussions-Potential issues with contamination within existing buildings. Funding requirements unclear
KirkwallK-29RedevelopmentPublicListed Building/structures on site - requirement for investigation. Updated masterplan/development brief requiredLong TermNo progress-Listed Building/structures. Would require specialist designers and potential external funding for delivery.
KirkwallK-30Business & Industrial/EducationalPublicUpdated development Brief required. Understanding of UHI expansions requirements needed.Long TermPartial developmentDevelopment of nursery consented on part of siteReview of land use as part of next LDP

Figure 1 - Map of Kirkwall Allocations

IMAGE: Map of Kirkwall showing the settlement boundary and allocation sites K-1 through K-30, including housing, business and industrial, mixed-use, redevelopment and educational allocations around Kirkwall, Hatston, St Ola and the surrounding coastline.

Stromness Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
StromnessSTR-1HousingPrivate-Long TermNo progress--
StromnessSTR-2HousingPublicAccess issues, requires full assessment and exploration of accessLong TermEarly discussions--
StromnessSTR-3HousingPrivateCulverted watercourse on site - drainage and flooding assessment required), Development Brief required for the site, Foul drainage capacity requires explorationLong TermEarly discussions--
StromnessSTR-4HousingPrivate-Long TermNo progress--
StromnessSTR-5HousingPrivate-Short TermConsentedApplication in for amendment to house location based on conditionsApplication approved (22/382/PP)
StromnessSTR-6HousingPrivate--Completed--
StromnessSTR-7HousingPrivate-Medium TermNo progress--
StromnessSTR-8HousingPublic-Medium TermPartially developedCare Home completedCare Home completed, rest of land undeveloped
StromnessSTR-9HousingPrivateDevelopment Brief requires update, inc. constraints impactLong TermNo progress-Application submitted on part of allocation (23/189/PP) - Refused
StromnessSTR-10HousingPrivate--Completed--
StromnessSTR-11Housing------
StromnessSTR-12HousingPublic-----
StromnessSTR-13Housing------
StromnessSTR-14HousingPrivateSouth End Dev Brief adopted.Medium TermNo progressLandowners issued with dev brief-
StromnessSTR-15HousingPrivateSouth End Dev Brief adopted.Medium TermNo progressLandowners issued with dev brief-
StromnessSTR-16HousingPrivateSouth End Dev Brief adopted. Infrastructure surveys inc. drainage, foul water and access required. Geological survey neededLong TermNo progressLandowners issued with dev briefMultiple Private owners. Integration into existing sewage network would be required. Access and road/path improvements required. Geological investigations needed
StromnessSTR-17HousingMixedSouth End Dev Brief adopted. Infrastructure surveys inc. drainage, foul water and access required. Geological survey neededLong TermNo progressLandowners issued with dev briefSite contains large area of marshland. Part Private, part OHAL ownership. Integration into existing sewage network would be required. Cross site pedestrian connections also required
StromnessSTR-18HousingPrivateSouth End Dev Brief adopted. Infrastructure surveys inc. drainage, foul water and access required. Geological survey neededLong TermNo progressLandowners issued with dev briefSteeply sloping areas of the site which are unsuitable for development. Access and internal connections need consideration. Green/Blue corridor along May Burn within site
StromnessSTR-20Business & IndustrialMixedNo Action Required----
StromnessSTR-21Business & IndustrialPublicNo Action Required----
StromnessSTR-22Business & IndustrialPublicNo Action Required----
StromnessSTR-23RedevelopmentPrivateNo Action Required-partially developed-Co-op redeveloped on northern end.
StromnessSTR-24RedevelopmentPrivateNo Action Required-early discussions--
StromnessSTR-25RedevelopmentPrivateNo Action Required-Early concept--
StromnessSTR-26RedevelopmentPrivateDevelopment Brief Required, Retention of historic building/structures required----

Figure 2 - Map of Stromness Allocations

IMAGE: Map of Stromness showing allocation sites STR-1 through STR-26 around the town, harbour, coastline, roads and surrounding areas.

Dounby Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
DounbyDY-1HousingPrivate-Short TermPartially developed-Partially developed, 1/2 plots remaining
DounbyDY-2HousingPrivate-Long TermNo Progress--
DounbyDY-3HousingPrivate-Short TermApplication Stages-Application submitted (23/383/PP) No decision
DounbyDY-4HousingPrivateWater Main crossing site - investigation required, Development Brief requiredMedium TermNo Progress--
DounbyDY-5HousingPrivateAccess requires exploration, foul and drainage studies required.Long TermNo Progress--
DounbyDY-6HousingPrivateRequested removal from next PlanN/ANo Progress--
DounbyDY-7HousingPrivateRequested removal from next PlanN/ANo Progress--

Figure 3 - Map of Dounby Allocations

IMAGE: Map of Dounby showing allocation sites DY-1 through DY-7 around the settlement, including roads, watercourses and surrounding land.

Finstown Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
FinstownF-1HousingMixedDevelopment Brief required, within HSE zone for the quarry, topography and level require investigation for good design and drainage requirements. Burn within top of site boundaryMedium TermNo progress--
FinstownF-2HousingPrivateDevelopment Brief required, Burn crossing site, drainage/flooding investigation required,Medium TermNo Progress--
FinstownF-3HousingPrivateDevelopment Brief required, Heritage and setting impact on Cuween Hill need to be considered, Watercourse within the site boundary - flooding and drainage study required and potential de-culverting works needed.Long TermNo Progress--
FinstownF-4HousingPrivateSetting of Cuween Hill needs to be considered.Long TermNo Progress--
FinstownF-5HousingPrivateAdjacent to Scheduled Monument, Impact of development on archaeology and heritage requires investigation, Water main within site boundary, Coastal flooding within site - flood assessment requiredLong TermNo Progress--

Figure 4 - Map of Finstown Allocations

IMAGE: Map of Finstown showing allocation sites F-1 through F-5 around the settlement, The Ouse, the A965 and surrounding watercourses, coastline and heritage areas.

St Margaret’s Hope Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
St Margaret's HopeSMH-1HousingPrivatePartially developed outLong TermPartially developed-One plot built out. One plot remaining
St Margaret's HopeSMH-2HousingPublic-Long TermNo Progress--
St Margaret's HopeSMH-3HousingPublic-Short TermEarly discussions-Hope Co-housing project
St Margaret's HopeSMH-4HousingPublic-Long TermNo Progress--
St Margaret's HopeSMH-5HousingPrivateFlooding and Drainage assessment required, Access and Transport access required.Long TermPre-app-Pre-app discussions have occurred on an area that covers part of the site

Figure 5 - Map of St Margaret’s Hope Allocations

IMAGE: Map of St Margaret’s Hope showing allocation sites SMH-1 through SMH-5 around the settlement, harbour, coastline, roads and surrounding land.

Stenness Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
StennessSTE-1HousingPrivateFlood and drainage assessment required due to surface water and flooding issuesLong TermNo progress--
StennessSTE-2HousingPrivate-Long TermNo progress--

Figure 6 - Map of Stenness Allocations

IMAGE: Map of Stenness showing allocation sites STE-1 and STE-2 on either side of the A965, with surrounding drainage, settlement and open land.

Toab Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
ToabTB-1HousingPrivate--Application Granted-Application (24/008/PP) granted for 10 homes
ToabTB-2HousingPrivate--Application Granted-Application (19/367/PP) granted for 16 homes
ToabTB-3HousingPrivateFlood Risk Assessment Required due to Coastal flooding locationMedium TermPartially developed--
ToabTB-4HousingPublicFlood Risk Assessment Required due to Coastal flooding locationMedium TermNo progress--
ToabTB-5HousingPrivateDrainage and foul water treatment capacity required assessment.Long TermNo progress--

Figure 7 - Map of Toab Allocations

IMAGE: Map of Toab showing allocation sites TB-1 through TB-5 along the A960 and the coastal area around Deer Sound, with drainage, mudflats and surrounding settlement.

Burray Village Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
Burray VillageBV-1HousingPrivate--Completed--
Burray VillageBV-2HousingPublicPedestrian access required to neighbouring housing to create off-road linkLong TermNo progress--
Burray VillageBV-3HousingPublicPedestrian access required from school to housing to create off-road linkLong TermNo progress--
Burray VillageBV-4HousingPrivateDevelopment brief required with BV-5. Drainage assessment required and consideration for neighbouring allocations and future infrastructure.Long TermNo progress--
Burray VillageBV-5HousingPrivateDevelopment brief required with BV-4. Drainage assessment required and consideration for neighbouring allocations and future infrastructure. Watercourse on-site (culverted) capacity and flood assessment required to inform design and infrastructureLong TermNo progress--
Burray VillageBV-6HousingPrivate-Short TermOn-site-Application 21/269/AMC granted

Figure 8 - Map of Burray Allocations

IMAGE: Map of Burray Village showing allocation sites BV-1 through BV-6 around the village, coastline, roads, school, playing field and surrounding watercourses.

Evie Village Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
Evie VillageEV-1HousingPrivate--Completed--
Evie VillageEV-2HousingPrivateCanalised burn within boundary, drainage and offset requirements needed to be exploredMedium TermNo progress--
Evie VillageEV-3HousingPrivateWater Main within boundary.Short TermApplication approved-Application 21/029/PP granted
Evie VillageEV-3HousingPrivateFuture connections to long term allocation required to be providedLong TermNo progress--
Evie VillageEV-5HousingPrivate-Long TermNo progress--

Figure 9 - Map of Evie Village Allocations

IMAGE: Map of Evie Village showing allocation sites EV-1 through EV-5 along the A966, including the settlement, watercourses, roads and surrounding land.

Orphir Village Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
OrphirOR-1HousingPrivate--Completed--
OrphirOR-2HousingPrivateFoul drainage capacity and connection options require assessmentMedium TermPartialPermission granted to one plot at front of siteSite in multiple ownership, part of the site granted planning permission 24/068/PP for one dwelling, access to rest of site still possible
OrphirOR-3HousingPrivateUtilities on-site, assessment required and permissions to move would be requiredLong TermNo Progress--
OrphirOR-4HousingPrivate--Completed--
OrphirOR-5HousingPrivateDrainage and flood risk assessment required on the site due to watercourse and well within boundary. Biodiversity value of parts of the site require assessmentLong TermNo Progress--
OrphirOR-6HousingPrivateAccess to the site might require road/junction improvementsLong TermNo Progress--

Figure 10 - Map of Orphir Allocations

IMAGE: Map of Orphir showing allocation sites OR-1 through OR-6 around the settlement and A964, including drains, a wind turbine, reservoir, school and surrounding land.

Quoyloo Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
QuoylooQ-1HousingPrivateFoul drainage capacity and connection options require assessmentMedium TermNo Progress--
QuoylooQ-2HousingPrivateFoul drainage capacity and connection options require assessment, including assessment of culverted drain within siteLong TermNo Progress--
QuoylooQ-3HousingPrivateFoul drainage capacity and connection options require assessmentLong TermNo Progress--
QuoylooQ-4HousingPrivateFoul drainage capacity and connection options require assessmentLong TermNo Progress--
QuoylooQ-5HousingPrivateFoul drainage capacity and connection options require assessmentLong TermNo Progress--
QuoylooQ-6HousingPrivateFoul drainage capacity and connection options require assessmentMedium TermPartialApplication granted on part of siteApplication 24/108/PP granted permission for 2 homes, western and northern part of the site undeveloped.
QuoylooQ-7HousingPrivateFoul drainage capacity and connection options require assessmentLong TermNo Progress--

Figure 11 - Map of Qouyloo Allocations

IMAGE: Map of Quoyloo showing allocation sites Q-1 through Q-7 around Quoyloo and Scarwell, with roads, drains and surrounding countryside.

St Mary’s Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
St Mary'sSTM-1HousingPrivateDevelopment Brief/masterplan required for STM-1, STM-2 and STM-3, STM-4 & STM-6 (potentially inc. STM-5), Drainage and flooding assessment required for whole site (potentially covering STM1-3), consideration of scheduled ancient monument to the west of the site, Access and Transport Assessment required due to scale of site. Pedestrian and vehicle connectivity between neighbouring allocations would be requiredLong TermNo Progress--
St Mary'sSTM-2HousingPrivateDevelopment Brief/masterplan required for STM-1, STM-2 and STM-3, STM-4 & STM-6 (potentially inc. STM-5), Drainage and flooding assessment required for whole site (potentially covering STM1-3), Access and Transport Assessment required due to scale of site. Pedestrian and vehicle connectivity between neighbouring allocations would be requiredLong TermNo Progress--
St Mary'sSTM-3HousingPrivateDevelopment Brief/masterplan required for STM-1, STM-2 and STM-3, STM-4 & STM-6 (potentially inc. STM-5), Drainage and flooding assessment required for whole site (potentially covering STM1-3), Access and Transport Assessment required due to scale of site. Pedestrian and vehicle connectivity between neighbouring allocations would be requiredLong TermNo Progress--
St Mary'sSTM-4HousingPrivateDevelopment Brief/masterplan required for STM-1, STM-2 and STM-3, STM-4 & STM-6 (potentially inc. STM-5), Drainage and flooding assessment required for whole site (potentially covering STM1-3), Access and Transport Assessment required due to scale of site. Pedestrian and vehicle connectivity between neighbouring allocations would be requiredLong TermNo Progress--
St Mary'sSTM-5HousingPublicDevelopment Brief/masterplan required for STM-1, STM-2 and STM-3, STM-4 & STM-6 (potentially inc. STM-5)Long TermNo Progress--
St Mary'sSTM-6HousingPublicDevelopment Brief/masterplan required for STM-1, STM-2 and STM-3, STM-4 & STM-6 (potentially inc. STM-5)Long TermNo Progress--
St Mary'sSTM-7HousingPrivateRoad and path improvements would be required to connect the site to the villageLong TermNo Progress--
St Mary'sSTM-8HousingPrivateRoad and path improvements would be required to connect the site to the villageLong TermNo Progress--

Figure 12 - Map of St Mary’s Allocations

IMAGE: Map of St Mary’s showing allocation sites STM-1 through STM-8 along the settlement and the Bay of Ayre, with the A961, coastline and surrounding land.

The Palace Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
The PalaceP-1HousingPrivateAccess from public road would require upgrade and improvements. Long-term issues surrounding coastal erosion and promoting land that requires access from at-risk roads/road sections. High potential for archaeological interest in the area, assessment required.Long TermNo Progress-Landscape and heritage sensitivities within the area due to numerous Scheduled Ancient Monuments, and historic/listed buildings. Consideration of appropriate of scale, massing, design and siting would be required for any development.
The PalaceP-2HousingPrivateFluvial and Surface Water Flooding to part of the site. Full drainage and flooding assessment required to consider appropriate areas for development. Highly constrained road network through village, road widening not feasible in places due to Heritage features and existing buildings. Review of appropriateness to promote land with highly constrained access should be continued as part of next LDP. High potential for archaeological interest in the area, assessment required.Long TermNo Progress-Landscape and heritage sensitivities within the area due to numerous Scheduled Ancient Monuments, landscape features and historic/listed buildings. Consideration of appropriate of development scale, massing, design and siting would be required for any development.
The PalaceP-3HousingPrivateHighly constrained road network through the village, widening not feasible in places due to Heritage features and existing buildings. Review of appropriateness to promote land with constrained access should be continued as part of next LDP. High potential for archaeological interest in the area, assessment required.Long TermNo Progress-Landscape and heritage sensitivities due to Scheduled Ancient Monuments, and historic/listed buildings. Consideration of appropriate of scale, massing, design and siting would be required for any development.
The PalaceP-4HousingPrivateHighly constrained road network through the village, widening not feasible in places due to Heritage features and existing buildings. Review of appropriateness to promote land with constrained access should be continued as part of next LDP. High potential for archaeological interest in the area, assessment required.Long TermNo Progress-Landscape and heritage sensitivities within the area due to numerous Scheduled Ancient Monuments, and historic/listed buildings. Consideration of appropriate of scale, massing, design and siting would be required for any development.

Figure 13 - Map of The Palace Allocations

IMAGE: Map of The Palace showing allocation sites P-1 through P-4 near the coastline, Palace Edens, Earl’s Palace, Bishop’s Palace and surrounding heritage features.

Burnside, Harray Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
Burnside, HarrayBH-1HousingPrivateRoad upgrades and widening would be required, drainage and foul assessment and shared infrastructure requiredLong TermNo Progress--
Burnside, HarrayBH-2HousingPrivateUtilities on-site, assessment required and permissions to move would be requiredMedium TermNo Progress--
Burnside, HarrayBH-3HousingPrivateUtilities on-site, assessment required and permissions to move would be requiredLong TermNo Progress--
Burnside, HarrayBH-4HousingPrivate-Short TermNo Progress-Single unit development within settlement boundary - would classify as infill

Figure 14 - Map of Burnside Allocations

IMAGE: Map of Burnside, Harray showing allocation sites BH-1 through BH-4 around Appietown, roads, Burn of Netherbrough, playing field and surrounding land.

Evie School Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
Evie SchoolES-1HousingPrivateAccess upgrades required to junction and road, visibility issues require consideration, Shared foul drainage requiredLong TermEarly discussions--
EVIE SCHOOLES-2HousingPrivateAccess upgrades required to junction and road, visibility issues require consideration, Shared foul drainage required.Long TermEarly discussions--
Evie SchoolES-3HousingPublicBurn offset required, drainage impact study needed, Access track upgrades potentially required. Shared foul drainage requiredMedium TermNo Progress--

Figure 15 - Map of Evie School Allocations

IMAGE: Map of Evie School showing allocation sites ES-1, ES-2 and ES-3 along the A966 near Redland and Standpretty, with the school, balancing pond, drains and surrounding land.

Madras Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
MadrasM-1HousingPrivateUpgrades to access points and roads requiredLong TermNo Progress--
MadrasM-2HousingPrivateUpgrades to access points and roads requiredLong TermNo Progress--
MadrasM-3HousingPrivateUpgrades to access points and roads requiredLong TermNo Progress--
MadrasM-4HousingPrivateWater Main within boundary.Long TermNo Progress--
MadrasM-5HousingPrivateWater Main within boundary.Long TermNo Progress--
MadrasM-6HousingPrivateJunction and road improvements required, visibility issues. Surface Water issuesLong TermNo Progress--

Figure 16 - Map of Madras Allocations

IMAGE: Map of Madras showing allocation sites M-2 through M-6 around Brough and Harray, with roads, watercourses and surrounding land.

Tingwall Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
TingwallTW-1HousingPrivateWatercourse within boundary, flooding and drainage assessment required to ensure no impact on neighbouring developmentLong TermNo Progress-Potential review as part of next LDP to assess alignment with local living policies
TingwallTW-2HousingPrivateHeritage and Archaeological impact assessment and exploration required to ensure no impact on the broch, potential coastal flooding and erosion issues, requires assessmentLong TermNo Progress-Location next to ferry terminal might be more appropriate for non-housing uses as part of review of LDP

Figure 17 - Map of Tingwall Allocations

IMAGE: Map of Tingwall showing allocation sites TW-1 and TW-2 around Tingwall, the Gorseness Road, coastline and surrounding watercourses.

Hillhead Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
HillheadHH-1HousingPublic--Completed--
HillheadHH-2HousingPrivateDrainage/foul infrastructure for whole site needs to be done. Capacity of Scottish Water drainage requires confirmationLong TermNo progress--
HillheadHH-3HousingPrivateDrainage/foul infrastructure for whole site needs to be done. Capacity of Scottish Water drainage requires confirmationLong TermNo progress--

Figure 18 - Map of Hillside Allocations

IMAGE: Map of Hillhead showing allocation sites HH-1, HH-2 and HH-3 along the B9050 and surrounding land.

Houton Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
HoutonHT-1HousingPublicDevelopment Brief required. Archaeological/heritage assessment, Drainage assessment, Shared foul sewage infrastructure, Upgrades to road network.Medium TermEarly discussionsDiscussions taken place regarding requirements for planning and infrastructure need-
HoutonHT-2HousingPrivateArchaeological/heritage assessment required due to onsite wartime features, potential contamination issues, Drainage assessment, Access to site requires exploration due to ferry terminal accessLong TermNo progress--
HoutonHT-3HousingPrivateArchaeological/heritage assessment required due to onsite wartime features, potential contamination issues, Drainage assessment, Access to site requires exploration due to ferry terminal accessLong TermNo progress--

Figure 19 - Map of Houton Allocations

IMAGE: Map of Houton showing allocation sites HT-1, HT-2 and HT-3 around the ferry terminal, Bay of Houton, A964, drains and surrounding land.

Lyron Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
LyronYL-1HousingPrivate-Long TermNo progress--

Figure 20 - Map of Lyron Allocations

IMAGE: Map of Lyron showing allocation site LY-1 beside the A966, with the settlement, hall, surrounding housing, watercourse and open land.

Norseman Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
NorsemanN-1HousingPrivate--On-site--
NorsemanN-2HousingPrivateDrainage and foul assessment required - low lying siteLong TermNo progress--
NorsemanN-3HousingPrivateDrainage and foul assessment required, environmental impact potential on sensitive soils/peatland/biodiversityLong TermNo progress--

Figure 21 - Map of Norseman Allocations

IMAGE: Map of Norseman showing allocation sites N-1, N-2 and N-3 along the road network, with drains and surrounding peatland and countryside.

Scapa Brae Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
Scapa BraeSB-1HousingPrivateWater Main within boundary - investigation with Scottish Water required with potential worksLong TermNo progress--
Scapa BraeSB-2HousingPrivate-Short TermApplication Granted-Applications 18/288/PP, 23/082/PP, 22/349/PP, 23/244/PP granted
Scapa BraeSB-3HousingPrivateWater Main within boundary - investigation with Scottish Water required with potential worksMedium TermNo progress--
Scapa BraeSB-4HousingPrivate--Completed--
Scapa BraeSB-5HousingPrivateWater Main within boundary - investigation with Scottish Water required with potential works. Private service pipes also within site, full investigations requiredMedium TermNo progress--

Figure 22 - Map of Scapa Brae Allocations

IMAGE: Map of Scapa Brae showing allocation sites SB-1 through SB-5 around Greenigoe and the A964, with drains, watercourses and surrounding land.

Dalespot Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
DalespotDA-1HousingPrivate-Medium TermApplications approved-Application 18/135/PP and 21/349/PP approved,

Figure 23 - Map of Dalespot Allocations

IMAGE: Map of Dalespot showing allocation site DA-1 beside the A961, with surrounding roads, drainage and countryside.

Herston Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
HerstonHE-1HousingPrivate-Medium TermEarly discussions--

Figure 24 - Map of Herston Allocations

IMAGE: Map of Herston showing allocation site HE-1 near the coast and the B9042, with surrounding open land and settlement.

Lighthouse Corner Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
Lighthouse CornerLC-1HousingPrivate-Medium TermPre-app--
Lighthouse CornerLC-2HousingPrivate-Medium TermPre-app--
Lighthouse CornerLC-3HousingPrivateCombined foul/drainage proposals required for proposals. Access upgrades required to be explored.Medium TermPre-app--

Figure 25 - Map of Lighthouse Corner Allocations

IMAGE: Map of Lighthouse Corner showing allocation sites LC-1, LC-2 and LC-3 beside the B9050 and surrounding roads, drainage and countryside.

Scorradale Proposals

SettlementSite NumberUseOwnershipActions needed for deliveryPipeline for DeliveryCurrent StageProgress NotesSite/General Notes
ScorradaleSC-1HousingPrivateAccess requires exploration with potential upgrades likely, shared drainage and foul assessment for shared infrastructureLong TermPre-app-High level pre-app discussions held with Landowner
ScorradaleSC-2HousingPrivateWater course within site boundary, shared drainage and foul assessment for shared infrastructureLong TermNo progress--
ScorradaleSC-3HousingPrivate-Short TermApplication Submitted-Application 22/365/PP, awaiting decision

Figure 26 - Map of Scorradale Allocations

IMAGE: Map of Scorradale showing allocation sites SC-1, SC-2 and SC-3 around Scorradale Road and the A964, with surrounding contours and watercourses.

Schedule 2 - Delivery Programme: Policies

Policy NumberPolicy NameAction Required?SG/PPA/DMGResponsibilityTarget DateProgressDate CompletedNote
Policy 1Criteria for All Development
Policy 2DesignDevelopment Briefs and Design StatementsPPADevelopment & Marine Planning, OIC2027Not CompletedReview as part of LDP - potential integration into next Plan within allocation/settlement plans
Policy 3Settlements, Town Centres & Primary Retail FrontagesTown Centre Health ChecksDMGDevelopment & Marine Planning, OICbi-annuallyNot CompletedTo be completed bi-annually. 2024 last completion
Policy 4Business, Industry & EmploymentEmployment Land AuditAudit - DMGDevelopment & Marine Planning, OICbi-annuallyNot CompletedLast completed 2023
Businesses out with town centresDMGDevelopment & Marine Planning, OIC2023CompletedSeptember 2023Completed in September 2023.
Business and Industry Land Research and potential StrategyDevelopment & Marine Planning, Ec Dev, OIC2027No CompletedIdentified as potential evidence gap for the next LDP
Vacant and Derelict Land AuditAudit - DMGDevelopment & Marine Planning, OICannually
Policy 5HousingHousing Land AuditAuditDevelopment & Marine Planning, OICbi-annuallyPreviewed as part of LDP2024 Housing Land Audit complete
Policy 6Advertisements & Signs
Policy 7EnergyEnergySGDevelopment & Marine Planning, OICCompleted2017Policy and guidance will be reviewed in line with NPF4 Policy as part of LDP review
Policy 8Historic Environment & Cultural HeritageHistoric Environment & Cultural HeritageSGDevelopment & Marine Planning, OICCompleted2017This SG is statutory after notification to the Scottish Ministers.
Review Conservation Areas and associated Management PlanPPADevelopment & Marine Planning, OICEarly within the next LDP periodNot CompletedThis will cover all the current conservation areas.
Policy 9Natural Heritage & LandscapeNatural EnvironmentSGDevelopment & Marine Planning, OICCompleted2017This SG is statutory after notification to the Scottish Ministers.
A full review of the Orkney Landscape Character AssessmentDMGSNHWhen required within the lifetime of the PlanNot CompletedThis is a SNH publication and therefore the review is in their hands
Considering and Including Biodiversity in DevelopmentDMGDevelopment & Marine Planning, OIC2024CompletedCompleted
Trees and WoodlandPPADevelopment & Marine Planning, OIC2025In progressOut for consultation
Policy 10Green InfrastructurePlanning for Open Space and Open Space Audit and ActionsPPADevelopment & Marine Planning, OICWhen required within the lifetime of the PlanNot Completed2014Initial documents were approved / completed in 2014. They require to be reviewed and updated as part of the next LDP
Core Path PlanDMGDevelopment & Marine Planning, OIC2018CompleteCore Path plan was amended in September 2018.
Play sufficiency AssessmentDevelopment & Marine Planning, OIC2027CompleteComplete as part of the Evidence Report for LDP
Policy 11Outdoor Sports, Recreation & Community FacilitiesPlanning for Open Space, Open Space Audit & Action ProgrammePPADevelopment & Marine Planning, OICNot CompletedInitial documents were approved / completed in 2014. They require to be reviewed and updated.
Policy 12Coastal DevelopmentOrkney Islands Regional Marine PlanSGMarine Planning2025In progressConsultative Draft produced and consultation complete.
AquacultureSGDevelopment & Marine Planning, OICNot CompletedPolicy and guidance will be reviewed and will seek alignment with the Marine Plan for the next LDP
Coastal Management Plan/Coastal Adaptation StudyPPAOICIn ProgressLIDAR works completed. Analysis in early stages. This would be a corporate document, completed with input from several OIC Teams.
Policy 13Flood Risk, SUDS & Waste Water DrainageLocal Flood Risk Management Plan - second wavePPADevelopment & Marine Planning and Engineering Service, OIC and SEPA2022Completed2022Completed 2022
Kirkwall Surface Water Management PlanEngineering Service (with support from planning)2025In progressWork currently underway on Kirkwall catchments and potential capacity within the networks. Completion of consultant work expected May 2025
Drainage and Roads Guidance/HandbookPPAOIC (DM, Engineering, Roads)2026Early stagesDiscussions/early works underway to compile Drainage Guidance in relation to Roads to support planning applications
Policy 14Transport, Travel & Road Network InfrastructureOrkney Local Transport Strategy and Delivery PlanSGTransport, OICCompleted2023Works from this strategy will feed into the next LDP review process
The Orkney Active Travel StrategyPPATransport, OIC2026Not CompletedOutlined within the Local Transport Strategy Delivery Plan for 2025/2026 production. Outcomes from this will be fed into the review of the next LDP.
All Policies-Will be monitored against use as part of LDP Review process-